BLD-Final | 2/2/2018 | 2/7/2018 | 2/7/2018 | P | PASS |
Tony Young
|
|
|
CHRIS - TONY DID PRELIMINARY Phone #: ###-####
|
DOC - Permit Finaled | 2/7/2018 | 2/7/2018 | 2/7/2018 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Aging Inspection | 12/27/2017 | 12/27/2017 | 12/29/2017 | | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 12/26/2017 | 12/26/2017 | 12/29/2017 | | PASS |
Tony Young
|
|
|
|
BLD-Conference | 11/14/2017 | 11/15/2017 | 11/15/2017 | A | PART |
Tony Young
|
|
|
Please call ahead for access, 1hr - Chris Phone #: ###-####,, ?s on guardrails
|
BLD-Other | 8/15/2017 | 8/15/2017 | 8/15/2017 | P | PASS |
Tony Young
|
|
|
Chris-fire stopping Phone #: ###-####
|
BLD-Wall cover | 8/10/2017 | 8/14/2017 | 8/14/2017 | A | FAIL |
Dave Hannah
|
|
|
Chris Phone #: ###-####,, chase fire blocks not done
|
BLD-Energy code compliance | 8/9/2017 | 8/10/2017 | 8/10/2017 | P | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, frame corrections complete,, need fire blocks in the chase of fireplace,, need full approval on the sprinkler system
|
BLD-Energy code compliance | 8/8/2017 | 8/9/2017 | 8/9/2017 | P | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, insulation ok,, need frame corrections complete and sprinkler full approval
|
BLD-Energy code compliance | 8/8/2017 | 8/8/2017 | 8/9/2017 | P | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, seal pack ok
|
BLD-Energy code compliance | 8/8/2017 | 8/8/2017 | 8/8/2017 | P | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, base layer on roof deck ok,, need sprinkler pass
|
BLD-Framing/Rough-in | 8/7/2017 | 8/8/2017 | 8/8/2017 | A | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, some minor corrections,, ok to start base layer
|
BLD-Framing/Rough-in | 8/7/2017 | 8/7/2017 | 8/7/2017 | P | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, a couple corrections
|
BLD-Framing/Rough-in | 8/4/2017 | 8/7/2017 | 8/7/2017 | A | PEND |
Tony Young
|
|
|
Chris Phone #: ###-####,, ok to start foam base layer,, needs sprinkler pass
|
BLD-Framing/Rough-in | 8/2/2017 | 8/4/2017 | 8/4/2017 | A | NR |
Tony Young
|
|
|
Chris Phone #: ###-####,, needs fire sprinklers 1st,, conf walk through only
|
BLD-Wall Bracing | 7/19/2017 | 7/20/2017 | 7/20/2017 | A | PASS |
Tony Young
|
|
|
Shear // Chris Phone #: ###-####
|
BLD-Wall Bracing | 7/18/2017 | 7/18/2017 | 7/18/2017 | P | PART |
Brandon Shaw
|
|
|
First and Second floor only, no access to Third story
|
BLD-Footing | 5/26/2017 | 5/26/2017 | 5/26/2017 | P | PASS |
Tony Young
|
|
|
Jared-pour time 2 Phone #: ###-####
|
BLD-Foundation | 5/2/2017 | 5/3/2017 | 5/3/2017 | P | PASS |
Dave Hannah
|
|
|
Jarod Phone #: ###-####
|
BLD-Footing | 4/24/2017 | 4/25/2017 | 4/25/2017 | P | PART |
Tony Young
|
|
|
Jared Phone #: ###-####,, work in progress
|