BLD-Final | 9/10/2018 | 9/11/2018 | 9/11/2018 | A | PASS |
Mike Jordan
|
|
|
Please call 30 min prior to inspection. Phone #: ###-#### Inspection requested via web by John Saucerman. the panic hardware has been installed. ok for perm occ.
|
BLD-Final | 9/6/2018 | 9/7/2018 | 9/7/2018 | A | FAIL |
Mike Jordan
|
|
|
Please call; 30 min prior to inspection Phone #: ###-#### Inspection requested via web by John Saucerman. Provided panic hardware on the south east exit door. Everything else ok.
|
FIRE-Final Inspection | 9/6/2018 | 9/6/2018 | 9/6/2018 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, fire alarm inspection is complete (FIR17-00512), fire extinguishers are placed with current inspection tags. Final life fire safety inspection complete.
Please call 30 min prior to inspection Phone #: ###-#### Inspection requested via web by John Saucerman
|
BLD-Ceiling Grid Inspection | 7/25/2018 | 7/26/2018 | 7/26/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by John Saucerman
|
BLD-Framing/Rough-in | 6/15/2018 | 6/15/2018 | 6/15/2018 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by John Saucerman. Interior steel stud framed walls ok. Needs to submit plan mod to reflect the adtional walls that have been aded.
|
BLD-Ceiling Grid Inspection | 5/7/2018 | 5/8/2018 | 5/8/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by John Saucerman. Lobby area grid ok.
|
BLD-Ceiling Grid Inspection | 5/4/2018 | 5/7/2018 | 5/7/2018 | P | CANC |
Mike Jordan
|
|
|
Ceiling grid in lobby. Phone #: ###-#### >> Inspection requested via web by Shane Treasure Inspection cancelled from web by: Shane Treasure
|
BLD-Ceiling Grid Inspection | 4/27/2018 | 4/30/2018 | 4/30/2018 | A | PASS |
Mike Jordan
|
|
|
Please call Shane at 208 954 4469 with any questions. Phone #: ###-#### Inspection requested via web by Shane Treasure
|
BLD-Framing/Rough-in | 3/15/2018 | 3/15/2018 | 3/15/2018 | P | PASS |
Mike Jordan
|
|
|
Please call prior to inspection Phone #: ###-#### Inspection requested via web by John Saucerman. Interior steel stud framed walls only ok, phase 2A.
|
BLD - Request for Extension | 2/8/2018 | 2/9/2018 | 2/9/2018 | A | PASS |
Mike Jordan
|
|
|
Paul Phone #: ###-####
|
BLD-Conference | 2/8/2018 | 2/9/2018 | 2/8/2018 | A | DONE |
Candy A. Nichols
|
|
|
this is a test inspection to see if it extends to permits expiration date
|
BLD-Final | 11/14/2017 | 11/14/2017 | 11/14/2017 | P | PART |
Mike Jordan
|
|
|
Please call 30 minutes prior to arrival for inspection Phone #: ###-#### Inspection requested via web by John Saucerman. Ok temp c of o-phase 2 will start in or about March 2018
|
FIRE-Final Inspection | 11/13/2017 | 11/14/2017 | 11/14/2017 | P | PART |
Troy Cobbley
|
|
|
Life safety for Phase I passed.
Please call 30 minutes prior to inspection Phone #: ###-#### Inspection requested via web by John Saucerman
|
FIRE-Final Inspection | 11/3/2017 | 11/6/2017 | 11/6/2017 | P | FAIL |
Troy Cobbley
|
|
|
For phase I to be passed I need exit discharge lights at the marked exits and per Carl Westfall a temporary occupant load sign of 49 for Room 106. This will allow only one exit required until the permanent exit path through phase 2 is finished
Phone #: ###-#### Inspection requested via web by John Saucerman
|
BLD-Ceiling Grid Inspection | 7/7/2017 | 7/10/2017 | 7/10/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by John Saucerman
|
BLD-Wall cover | 6/2/2017 | 6/5/2017 | 6/5/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by John Saucerman
|
BLD-Wall cover | 5/31/2017 | 6/1/2017 | 6/1/2017 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by John Saucerman. work in progress on 1st. layer, ok.
|
BLD-Framing/Rough-in | 5/30/2017 | 5/31/2017 | 5/31/2017 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by John Saucerman. Interior steel stud walls for infills and new conferance rooms phase 1. provide UL listed and approved plumbing boxes for 2hr. wall.
|