BLD-Final | 8/24/2017 | 8/25/2017 | 8/25/2017 | P | PASS |
Dave Hannah
|
|
|
Roco Phone #: ###-####
|
FIRE-Final Inspection | 8/24/2017 | 8/24/2017 | 8/24/2017 | A | PASS |
Jim Page
|
|
|
Previously noted fire alarm issues have been repaired and final inspection complete. Final life fire safety inspection passed/complete.
|
BLD-Final | 6/30/2017 | 6/30/2017 | 6/30/2017 | P | DONE |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 6/29/2017 | 6/30/2017 | 6/30/2017 | A | PART |
Jim Page
|
|
|
TCO authorized for 30 days per conversation with Scott Arellano, FIR permit is in review status for minor fire alarm modifications, TCO is contingent on fire alarm modifications being completed, a final inspection performed and fire alarms passing inspection. Fire sprinkler inspection is complete, fire extinguishers are in place with current inspection tags. Fire life safety inspection complete for TCO, fire alarm inspection to be completed when FIR perimit is issued.
|
FIRE-Final Inspection | 6/28/2017 | 6/29/2017 | 6/29/2017 | A | CANC |
Jim Page
|
|
|
Final life fire safety inspection cannot be completed until a fire alarm contractor is contacted and modifications are made to the existing fire system as stated in the fire plan review comments, this inspection request is cancelled.
|
BLD-Final | 6/27/2017 | 6/28/2017 | 6/28/2017 | P | NR |
Dave Hannah
|
|
|
Mark Phone #: ###-#### needs fire final first
|
FIRE-Final Inspection | 6/27/2017 | 6/28/2017 | 6/28/2017 | A | FAIL |
Jim Page
|
|
|
Modifications need to be made to the existing fire alarm system, life fire safety inspection cannot be completed until fire alarm modifications have been made, inspected and passed.
|
BLD-Ceiling Grid Inspection | 6/22/2017 | 6/22/2017 | 6/23/2017 | P | PASS |
Dave Hannah
|
|
|
Mark Phone #: ###-####
|
BLD-Framing/Rough-in | 5/23/2017 | 5/23/2017 | 5/24/2017 | P | PEND |
Dave Hannah
|
|
|
Mark Phone #: ###-#### ok after elec rough in
|