Permit Information
Permit NumberBLD17-00666
StatusFinaled
Name GUHO CORP
Site Address 5015 N EUGENE ST
Project NameJames Castle House
Customer Number 
ePlanReviewYes
Description
(JAMES CASTLE HOUSE) **Project Management - Ron Hill** MODIFICATION TO THE FLOOR SYSTEM IN THE EXISTING STRUCTURE** Structural renovation of existing residential building including new concrete foundation. Construction of wood-framed addition at the south and west sides of existing building. New site amenities throughout lot. This building is fully fire sprinklered for R-3 occupancy.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/15/20182/16/20182/16/2018APASS
DetailsTony Young
Phil Phone #: ###-####
BLD-Final2/6/20182/7/20182/7/2018APART
DetailsTony Young
phil Phone #: ###-####,, temp occ ok,, just needs smoke detector
FIRE-Final Inspection2/5/20182/6/20182/6/2018APASS
DetailsJim Page
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags, knox box is located by the fire bell and PIV. Final life fire safety inspection complete.
BLD-Energy code compliance11/21/201711/22/201711/22/2017APASS
DetailsTony Young
Phil Phone #: ###-####
BLD-Framing/Rough-in11/20/201711/21/201711/21/2017APASS
DetailsTony Young
Phil Phone #: ###-####
BLD-Framing/Rough-in11/14/201711/15/201711/15/2017PPART
DetailsTony Young
Phil Phone #: ###-####,, walls ok to insulate,, fire blocking with insulation
BLD-Other10/31/201711/1/201711/1/2017APASS
DetailsDave Hannah
Energy for roof // Phil Phone #: ###-####
BLD-Wall Bracing10/24/201710/24/201710/24/2017PPART
DetailsTony Young
Shear // Phil Phone #: ###-####,, exterior sheet rock on west side ok,, exterior plywood shear and roof nailing ok,, work in progress
BLD-Wall Bracing10/17/201710/17/201710/17/2017PPART
DetailsTony Young
Phil Phone #: ###-####,, hold down and connection straps ok to cover with plywood
BLD-Footing9/5/20179/6/20179/6/2017APART
DetailsBrandon Shaw
South and East footings, MTI on site, need report filed before final
BLD-Foundation8/14/20178/14/20178/14/2017PPART
DetailsBrandon Shaw
Foundation for the existing home ok,, work in progress
BLD-Footing8/3/20178/4/20178/4/2017PPART
DetailsTony Young
Dan Phone #: ###-####,, footings for the existing home ok,, work in progress,, viewed compaction test results,, ok
BLD-Conference7/13/20177/13/20177/13/2017PPASS
DetailsTony Young
Dan Phone #: ###-####,, general ?s,, also looked at new floor joists, ok,, work in progress