Information based on query as of Thursday, June 27, 2024.
Permit Information
Permit NumberBLD17-00763
StatusFinaled
Name JORDAN WILCOMB CONSTRUCTION
Site Address 7552 W VICTORY RD
Project NameVictory Building - Shell
Customer Number 
ePlanReviewYes
Description
(VICTORY BUILDING) (DRH16-00547) The fire sprinkler system is used for building area increase and for fire area. To construct a 21,885 square foot shell building for future occupancy under separate tenant improvement permits. Work is to include concrete footings, concrete foundation, concrete piers, concrete slab on grade, exterior concrete sidewalks and aprons, uninsulated 56 inch tall masonry exterior walls, steel beams, steel columns, steel moment frames, steel roof purlins, steel cross bracing, horizontal steel wall purlins, steel exterior wall panels, steel roof panels, liner roof insulation system, wall insulation, a 1-hr fire-resistance-rated fire sprinkler riser room, exterior side-hinged swinging doors, exterior overhead doors, exterior windows, pipe bollards at overhead doors, and exterior awnings. A masonry trash enclosure will also be constructed. Special Inspection is required for soils, concrete, and steel (bolting and welding). This is a shell permit only. This permit is not intended to establish a Certificate of Occupancy for any tenant. Occupancy will be established under future tenant improvement permits. Separate racking permits will also be required if racks are to be installed. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13. A separate fire sprinkler permit shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/7/201712/8/201712/8/2017PPASS
DetailsJim Sly
Ready for Final on Core and Shell. Also note that a request for Final on BLD-02486 (TI space) in same building for afternoon was submitted. Allows for one visit to see both at same time. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Mark Steen
DOC - Permit Finaled12/8/201712/8/201712/8/2017PPASS
DetailsJim Sly
FIRE-Final Inspection12/6/201712/7/201712/7/2017PPASS
DetailsTroy Cobbley
Bldg shell fire/life safety passed. Contractor is going to provide fire dept access signage tomorrow. WIll be verified with the T.I. final inspection
BLD-Footing9/19/20179/20/20179/21/2017PCANC
DetailsMike Jordan
We anticipate being ready for inspection around 3pm Wednesday and plan to pour trash enclosure ftgs. Thursday am. Note, MTI checked sub grade ok. Thanks Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls
BLD-Framing/Rough-in9/14/20179/15/20179/15/2017APART
DetailsJim Sly
Framing riser room, thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls
Riser Room....OK
BLD-Wall cover9/6/20179/7/20179/7/2017APASS
DetailsMike Jordan
Exterior insulation Phone #: ###-#### Inspection requested via web by Kareen Falls
BLD-Energy code compliance9/7/20179/7/20179/7/2017APASS
DetailsMike Jordan
Exterior insulation Phone #: ###-#### Inspection requested via web by Kareen Falls. remainder of building ok.
BLD-Wall cover8/30/20178/31/20178/31/2017PPART
DetailsMike Jordan
ELec Insp to be requested for Thurs am
North ext. wall ready for early afternoon Insp
Thanks, Mark Steen
Phone #: ###-#### Inspection requested via web by Kareen Falls. North wall.
BLD-Conference8/10/20178/10/20178/10/2017AFAIL
DetailsBill VanDegrift
needs to address backwater valve on sewer before paving
BLD-Concrete8/2/20178/3/20178/3/2017PPASS
DetailsMike Jordan
SOG scheduled to pour 350 yds. 4am Friday. MTI to inspect and test concrete. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Vapor barrier ok.
BLD-Foundation7/19/20177/21/20177/21/2017ADEFR
DetailsMike Jordan
MTI scheduled to Insp rebar and concrete at lines 1 west ; A. Concrete scheduled for 1:00pm. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Ok pending special inspection.
BLD-Footing7/19/20177/20/20177/20/2017ACANC
DetailsMike Jordan
BLD-Footing7/18/20177/19/20177/19/2017ADEFR
DetailsMike Jordan
MTI scheduled for rebar Insp and concrete testing. Grid line A ftgs scheduled for concrete at 1pm Wed., thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Will have special inspection.
BLD-Footing7/13/20177/17/20177/17/2017APASS
DetailsMike Jordan
MTI to Insp rebar and test concrete at line 2 west. Concrete scheduled for noon Monday. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Footings on gridlines 1 and 2 from grids A to H. Will have special inspection.
BLD-Foundation7/13/20177/14/20177/14/2017APASS
DetailsMike Jordan
Concrete scheduled noon Friday. MTI to Insp rebar and test concrete. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. South Stemwall.
BLD-Foundation7/10/20177/11/20177/12/2017PPART
DetailsJim Sly
Concrete scheduled for 9am Wed, July 12th with MTI special Insp of rebar and concrete testing. Thanks Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls
OK pending MTI special inspection, tests and approvals.
BLD-Footing7/6/20177/7/20177/7/2017APART
DetailsBrandon Shaw
Line 2, spread footings
BLD-Footing7/5/20177/6/20177/6/2017APART
DetailsMike Jordan
Concrete scheduled for 10:30am Thursday. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. South footing, concrete placement started when arried on site. Special inspetor onn site.
BLD-Footing6/30/20177/5/20177/5/2017ACANC
DetailsMike Jordan
Concrete scheduled at noon. Thanks Phone #: ###-#### >> Inspection requested via web by Kareen Falls Inspection cancelled from web by: Kareen Falls
BLD-Footing6/28/20176/29/20176/29/2017APART
DetailsMike Jordan
Steel anticipated in place by 10:00am. Concrete scheduled at noon. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Work in progress on fotings on gridlineQ grids 1 to 3, grid 1 from grids o to Q and grid 1 from grid M to Q.
BLD-Footing6/27/20176/28/20176/28/2017PNR
DetailsMike Jordan
3:30 pm is best. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls
BLD-Footing6/15/20176/16/20176/16/2017PNR
DetailsJim Storey
Mark Steen is onsite Superintedent contact. Phone #: ###-#### Inspection requested via web by Kareen Falls