BLD-Final | 12/7/2017 | 12/8/2017 | 12/8/2017 | P | PASS |
Jim Sly
|
|
|
Ready for Final on Core and Shell. Also note that a request for Final on BLD-02486 (TI space) in same building for afternoon was submitted. Allows for one visit to see both at same time. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Mark Steen
|
DOC - Permit Finaled | 12/8/2017 | 12/8/2017 | 12/8/2017 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 12/6/2017 | 12/7/2017 | 12/7/2017 | P | PASS |
Troy Cobbley
|
|
|
Bldg shell fire/life safety passed. Contractor is going to provide fire dept access signage tomorrow. WIll be verified with the T.I. final inspection
|
BLD-Footing | 9/19/2017 | 9/20/2017 | 9/21/2017 | P | CANC |
Mike Jordan
|
|
|
We anticipate being ready for inspection around 3pm Wednesday and plan to pour trash enclosure ftgs. Thursday am. Note, MTI checked sub grade ok. Thanks Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls
|
BLD-Framing/Rough-in | 9/14/2017 | 9/15/2017 | 9/15/2017 | A | PART |
Jim Sly
|
|
|
Framing riser room, thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls Riser Room....OK
|
BLD-Wall cover | 9/6/2017 | 9/7/2017 | 9/7/2017 | A | PASS |
Mike Jordan
|
|
|
Exterior insulation Phone #: ###-#### Inspection requested via web by Kareen Falls
|
BLD-Energy code compliance | 9/7/2017 | 9/7/2017 | 9/7/2017 | A | PASS |
Mike Jordan
|
|
|
Exterior insulation Phone #: ###-#### Inspection requested via web by Kareen Falls. remainder of building ok.
|
BLD-Wall cover | 8/30/2017 | 8/31/2017 | 8/31/2017 | P | PART |
Mike Jordan
|
|
|
ELec Insp to be requested for Thurs am North ext. wall ready for early afternoon Insp Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. North wall.
|
BLD-Conference | 8/10/2017 | 8/10/2017 | 8/10/2017 | A | FAIL |
Bill VanDegrift
|
|
|
needs to address backwater valve on sewer before paving
|
BLD-Concrete | 8/2/2017 | 8/3/2017 | 8/3/2017 | P | PASS |
Mike Jordan
|
|
|
SOG scheduled to pour 350 yds. 4am Friday. MTI to inspect and test concrete. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Vapor barrier ok.
|
BLD-Foundation | 7/19/2017 | 7/21/2017 | 7/21/2017 | A | DEFR |
Mike Jordan
|
|
|
MTI scheduled to Insp rebar and concrete at lines 1 west ; A. Concrete scheduled for 1:00pm. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Ok pending special inspection.
|
BLD-Footing | 7/19/2017 | 7/20/2017 | 7/20/2017 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Footing | 7/18/2017 | 7/19/2017 | 7/19/2017 | A | DEFR |
Mike Jordan
|
|
|
MTI scheduled for rebar Insp and concrete testing. Grid line A ftgs scheduled for concrete at 1pm Wed., thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Will have special inspection.
|
BLD-Footing | 7/13/2017 | 7/17/2017 | 7/17/2017 | A | PASS |
Mike Jordan
|
|
|
MTI to Insp rebar and test concrete at line 2 west. Concrete scheduled for noon Monday. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Footings on gridlines 1 and 2 from grids A to H. Will have special inspection.
|
BLD-Foundation | 7/13/2017 | 7/14/2017 | 7/14/2017 | A | PASS |
Mike Jordan
|
|
|
Concrete scheduled noon Friday. MTI to Insp rebar and test concrete. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. South Stemwall.
|
BLD-Foundation | 7/10/2017 | 7/11/2017 | 7/12/2017 | P | PART |
Jim Sly
|
|
|
Concrete scheduled for 9am Wed, July 12th with MTI special Insp of rebar and concrete testing. Thanks Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls OK pending MTI special inspection, tests and approvals.
|
BLD-Footing | 7/6/2017 | 7/7/2017 | 7/7/2017 | A | PART |
Brandon Shaw
|
|
|
Line 2, spread footings
|
BLD-Footing | 7/5/2017 | 7/6/2017 | 7/6/2017 | A | PART |
Mike Jordan
|
|
|
Concrete scheduled for 10:30am Thursday. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. South footing, concrete placement started when arried on site. Special inspetor onn site.
|
BLD-Footing | 6/30/2017 | 7/5/2017 | 7/5/2017 | A | CANC |
Mike Jordan
|
|
|
Concrete scheduled at noon. Thanks Phone #: ###-#### >> Inspection requested via web by Kareen Falls Inspection cancelled from web by: Kareen Falls
|
BLD-Footing | 6/28/2017 | 6/29/2017 | 6/29/2017 | A | PART |
Mike Jordan
|
|
|
Steel anticipated in place by 10:00am. Concrete scheduled at noon. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls. Work in progress on fotings on gridlineQ grids 1 to 3, grid 1 from grids o to Q and grid 1 from grid M to Q.
|
BLD-Footing | 6/27/2017 | 6/28/2017 | 6/28/2017 | P | NR |
Mike Jordan
|
|
|
3:30 pm is best. Thanks, Mark Steen Phone #: ###-#### Inspection requested via web by Kareen Falls
|
BLD-Footing | 6/15/2017 | 6/16/2017 | 6/16/2017 | P | NR |
Jim Storey
|
|
|
Mark Steen is onsite Superintedent contact. Phone #: ###-#### Inspection requested via web by Kareen Falls
|