BLD-Final | 1/3/2018 | 1/4/2018 | 1/4/2018 | A | PASS |
Jim Storey
|
|
|
Dale Phone #: ###-####
|
FIRE-Final Inspection | 1/3/2018 | 1/4/2018 | 1/4/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Per fire dept the second gate Opticon is functional.
Dale Phone #: ###-####
|
FIRE-Final Inspection | 12/28/2017 | 12/29/2017 | 12/29/2017 | P | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with Dale Phone #: ###-####, inspection request will be rescheduled for a later date.
|
BLD-Final | 12/28/2017 | 12/29/2017 | 12/29/2017 | P | CANC |
Brandon Shaw
|
|
|
Dale Phone #: ###-####
|
BLD-Final | 12/21/2017 | 12/22/2017 | 12/22/2017 | P | FAIL |
Jim Storey
|
|
|
Dale Phone #: ###-#### need fire sign off
|
FIRE-Final Inspection | 12/21/2017 | 12/22/2017 | 12/22/2017 | P | CANC |
Jim Page
|
|
|
South side gate opticon sensor tested okay with fire department, other gate was still being worked on, fire department was not able to test other sensor. Inspection request will need to be rescheduled when other sesnor can be tested. This inspection request is cancelled.
|
BLD-Final | 11/14/2017 | 11/15/2017 | 11/15/2017 | P | PART |
Jim Storey
|
|
|
dale Phone #: ###-#### office/lounge only ok for temp.
|
FIRE-Final Inspection | 11/14/2017 | 11/15/2017 | 11/15/2017 | A | PART |
Troy Cobbley
|
|
|
A temp for life safety is ok with Scott until both opticon systems at the two gates have been tested.
dale Phone #: ###-####
|
BLD-Framing/Rough-in | 9/26/2017 | 9/27/2017 | 9/27/2017 | A | PASS |
Jim Storey
|
|
|
metal framing // Dale Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/15/2017 | 9/18/2017 | 9/18/2017 | A | PASS |
Jim Storey
|
|
|
Dale Phone #: ###-####
|
BLD-Framing/Rough-in | 8/10/2017 | 8/10/2017 | 8/10/2017 | P | PASS |
Jim Storey
|
|
|
Dale Phone #: ###-#### trusses added per plan west of exstining bldg.
|
BLD-Footing | 8/3/2017 | 8/4/2017 | 8/4/2017 | A | PART |
Brandon Shaw
|
|
|
9/10am-Dale Phone #: ###-####
|
BLD-Framing/Rough-in | 8/1/2017 | 8/2/2017 | 8/2/2017 | A | PASS |
Jim Storey
|
|
|
Dale Phone #: ###-#### pending trades
|
BLD-Other | 7/25/2017 | 7/26/2017 | 7/26/2017 | A | PASS |
Jim Storey
|
|
|
Dale-CMU Block Phone #: ###-####cmu and 3 hr wall progrestion of gyp ok to cover
|
BLD-Framing/Rough-in | 7/17/2017 | 7/17/2017 | 7/17/2017 | P | PASS |
Jim Storey
|
|
|
coreboard in attic ok pending 5/8 layers
|
BLD-Framing/Rough-in | 7/17/2017 | 7/17/2017 | 7/17/2017 | P | NH |
Jim Storey
|
|
|
dale Phone #: ###-####no access left message
|
BLD-Footing | 6/28/2017 | 6/29/2017 | 6/29/2017 | A | PART |
Brandon Shaw
|
|
|
Dale Phone #: ###-#### Lower section of inspection pit
|
BLD-Footing | 6/22/2017 | 6/23/2017 | 6/23/2017 | A | PART |
Jim Storey
|
|
|
Dale-rebar Phone #: ###-####wip si on site
|