BLD-Final | 8/15/2018 | 8/15/2018 | 8/15/2018 | P | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-#### final ok pending others
|
FIRE-Final Inspection | 8/14/2018 | 8/15/2018 | 8/15/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection complete.
Tom Phone #: ###-####
|
FIRE-Final Inspection | 8/13/2018 | 8/14/2018 | 8/14/2018 | A | CANC |
Troy Cobbley
|
|
|
Life safety will be ok to pass when the project related fire alarm and fire sprinkler permits are finaled.
Tom Phone #: ###-####
|
BLD-Final | 8/10/2018 | 8/13/2018 | 8/13/2018 | A | CANC |
Jim Storey
|
|
|
Tom Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/18/2018 | 7/18/2018 | 7/18/2018 | P | PASS |
Mike Jordan
|
|
|
2nd floor // Tom Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 6/25/2018 | 6/25/2018 | 6/25/2018 | P | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-####
|
BLD-Framing/Rough-in | 6/7/2018 | 6/7/2018 | 6/7/2018 | P | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-#### 2nd floor ok
|
BLD-Energy code compliance | 5/10/2018 | 5/11/2018 | 5/11/2018 | A | PART |
Brandon Shaw
|
|
|
Second floor exterior walls to window sill and South East stair landing
|
BLD-Energy code compliance | 4/24/2018 | 4/25/2018 | 4/25/2018 | A | PASS |
Jim Storey
|
|
|
roof insulation // Tom Phone #: ###-#### c/n made good// insulation ok to cover
|
BLD-Energy code compliance | 4/23/2018 | 4/23/2018 | 4/23/2018 | P | PEND |
Dave Hannah
|
|
|
roof insulation // ###-#### Tom spray on insulation ok but need to remove paper backed insulation
|
BLD-Energy code compliance | 4/13/2018 | 4/13/2018 | 4/13/2018 | P | PART |
Jim Storey
|
|
|
Tom Phone #: ###-#### 1st floor ok
|
BLD-Framing/Rough-in | 4/9/2018 | 4/9/2018 | 4/9/2018 | P | PASS |
Jim Storey
|
|
|
elevator shaft-Tom Phone #: ###-####first floor ok
|
BLD-Wall Bracing | 3/30/2018 | 4/2/2018 | 4/2/2018 | A | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-#### sheer walls at drive thru as well as frame ok ok to cover.
|
BLD-Other | 3/20/2018 | 3/21/2018 | 3/21/2018 | A | PASS |
Brandon Shaw
|
|
|
roof shear for drive-thru
|
BLD-Other | 3/16/2018 | 3/16/2018 | 3/16/2018 | P | PASS |
Jim Storey
|
|
|
roof nailing // Tom Phone #: ###-####
|
BLD-Other | 3/5/2018 | 3/6/2018 | 3/6/2018 | A | PASS |
Jim Storey
|
|
|
Tom-inspection to look at the metal trusses to cover Phone #: ###-#### wip truss framing ok to cover
|
BLD-Other | 2/21/2018 | 2/22/2018 | 2/22/2018 | A | PASS |
Jim Storey
|
|
|
Tom-exterior stud framing-this has nothing to do with the plan mod that''s in for review Phone #: ###-#### exterior framing ok to start cover/
|
BLD-Other | 1/25/2018 | 1/26/2018 | 1/26/2018 | P | PART |
Jim Storey
|
|
|
Welding - Tom Phone #: ###-#### work in progress/ need to finsh si insp.
|
BLD-Foundation | 11/21/2017 | 11/21/2017 | 11/21/2017 | P | PASS |
Jim Storey
|
|
|
insulation for foundation - Tom Phone #: ###-####
|
BLD-Foundation | 11/9/2017 | 11/9/2017 | 11/9/2017 | P | PART |
Jim Storey
|
|
|
Tom Phone #: ###-#### placed w/si pending report
|
BLD-Footing | 10/26/2017 | 10/27/2017 | 10/27/2017 | P | PASS |
Jim Storey
|
|
|
footing rebar // Tom Phone #: ###-#### ok pending si report for compaction/rebar and concrete
|