BLD-Final | 7/20/2017 | 7/21/2017 | 7/21/2017 | P | PASS |
Mike Jordan
|
|
|
please call for access Phone #: ###-#### Inspection requested via web by matthew greenman. Ok for perm oc.
|
FIRE-Final Inspection | 7/20/2017 | 7/21/2017 | 7/21/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Per discussion with the contractor the thumbturn dead bolt on the Stockroom door to be removed prior to a building inspection. ADA single action hardware can be installed as per discussion
|
FIRE-Final Inspection | 7/19/2017 | 7/20/2017 | 7/20/2017 | A | FAIL |
Troy Cobbley
|
|
|
I stopped at the job site after making two non-answered phone calls to the contact. I spoke to an employee and the ceiling tile installer. There were no approved plans available, ceiling tile was not installed, sprinkler permit not finaled, smoke evac not ready for testing...ect.
Eric Murphy Phone #: ###-####
|
BLD-Framing/Rough-in | 7/6/2017 | 7/7/2017 | 7/7/2017 | P | PART |
Mike Jordan
|
|
|
call for access please Phone #: ###-#### Inspection requested via web by matthew greenman. Needs to resubmit for roll up door and framing around door and engineering.
|
BLD-Ceiling Grid Inspection | 6/20/2017 | 6/21/2017 | 6/21/2017 | A | PART |
Mike Jordan
|
|
|
Please call for access Thanks, Phone #: ###-#### Inspection requested via web by matthew greenman. pending ele. and fire sprinkler.
|