FIRE-Final Inspection | 5/15/2018 | 5/15/2018 | 5/15/2018 | P | PASS |
Jim Page
|
|
|
Final life fire safety inspection complete.
2nd Floor reception door mag lock replaced with electric strike Phone #: ###-#### Inspection requested via web by Steve Jones
|
BLD-Final | 3/19/2018 | 3/19/2018 | 3/20/2018 | P | PART |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Jones OK for Temp. Occ. See previous Fire inspectors notes.
|
FIRE-Final Inspection | 3/16/2018 | 3/19/2018 | 3/19/2018 | A | PART |
Troy Cobbley
|
|
|
A temporary for life safety is being given with Assistant Chief Ron's permission until the two pre-action systems/rooms have been addressed. Per the contractor the smoke detectors are active in these rooms. They will need to remain active until the associated pre-action system is functional.
|
FIRE-Conference | 2/1/2018 | 2/1/2018 | 2/1/2018 | P | DONE |
Troy Cobbley
|
|
|
We discussed life safety items such as possible exit discharge lighting and interconnection of the access control egress locks with the new fire alarm system
|
BLD-Wall cover | 12/20/2017 | 12/20/2017 | 12/20/2017 | P | PASS |
Jim Sly
|
|
|
Inspection requested via web by Steve Jones
|
BLD-Framing/Rough-in | 11/22/2017 | 11/22/2017 | 11/22/2017 | P | PASS |
Mike Jordan
|
|
|
Northeast quadrant offices. Phone #: ###-#### Inspection requested via web by Steve Jones. North west wing interior steel stud framed walls ok. Hard lid in main lobby ok, pending lectrical and fire .
|
BLD-Framing/Rough-in | 11/16/2017 | 11/16/2017 | 11/16/2017 | P | PASS |
Jim Sly
|
|
|
1st Floor East of Lobby Phone #: ###-#### Inspection requested via web by Steve Jones
|