BLD-Final | 4/23/2019 | 4/23/2019 | 4/23/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 4/14/2019 | 4/15/2019 | 4/15/2019 | P | PART |
Tony Young
|
|
|
Need final life safety, landscaping, zoning, and building. Any questions please call Andy at ###-####. Phone #: ###-#### Inspection requested via web by Andy Eells,, ok pending others for a perm. c of o
|
FIRE-Final Inspection | 4/15/2019 | 4/15/2019 | 4/15/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection complete.
Andy Phone #: ###-####
|
BLD-Energy code compliance | 1/17/2019 | 1/17/2019 | 1/17/2019 | P | PASS |
Dave Hannah
|
|
|
Insulation inspection first floor approved plans are under stairs. If you have any questions please call Andy at ###-#### Phone #: ###-#### Inspection requested via web by Andy Eells
|
BLD-Energy code compliance | 1/16/2019 | 1/17/2019 | 1/17/2019 | A | PASS |
Dave Hannah
|
|
|
Insulation inspection first floor approved plans are under stairs. If you have any questions please call Andy at ###-#### Phone #: ###-#### Inspection requested via web by Andy Eells
|
BLD-Energy code compliance | 1/15/2019 | 1/15/2019 | 1/15/2019 | A | PASS |
Dave Hannah
|
|
|
3rd floor and 2nd floor ready possibly 1st depending on inspection time. Plans under stairs in mechanical room lock box code CORE. please call ahead so I can meet you there. Andy 2086317535 Phone #: ###-#### Inspection requested via web by Andy Eells
|
BLD-Framing/Rough-in | 1/8/2019 | 1/8/2019 | 1/9/2019 | P | PASS |
Dave Hannah
|
|
|
Andy Phone #: ###-####
|
BLD-Wall cover | 11/26/2018 | 11/26/2018 | 11/26/2018 | P | PASS |
Tony Young
|
|
|
Partial framing for soffit cover. Wanting to cover all exterior soffits and overhangs before full framing. Plans and engineering under stairs. Call Andy with any questions Phone #: ###-#### Inspection requested via web by Andy Eells
|
BLD-Wall cover | 11/9/2018 | 11/13/2018 | 11/13/2018 | A | PASS |
Tony Young
|
|
|
Remainder of exterior sheetrock. Jim looked at first level and second story walkway. Approved plans under stairs in garage. Phone #: ###-#### Inspection requested via web by Andy Eells
|
BLD-Wall cover | 11/8/2018 | 11/8/2018 | 11/8/2018 | P | PART |
Tony Young
|
|
|
Need partial exterior drywall nailing inspection. Please call with questions ###-#### Phone #: ###-#### Inspection requested via web by Andy Eells,, lower sections on exterior ok
|
BLD-Wall Bracing | 11/2/2018 | 11/5/2018 | 11/5/2018 | P | CANC |
Dave Hannah
|
|
|
MTI special inspection on shear scheduled at 2pm. the 5th. Phone #: ###-#### Inspection requested via web by Andy Eells hold downs and stapes ok
|
BLD-Conference | 9/5/2018 | 9/6/2018 | 9/6/2018 | A | PEND |
Dave Hannah
|
|
|
Give me a call to meet onsite to go over questions on fire rated wall detail. Thank You Andy Eells ###-#### Phone #: ###-#### Inspection requested via web by Andy Eells
|
BLD-Foundation | 8/1/2018 | 8/2/2018 | 8/2/2018 | A | PASS |
Dave Hannah
|
|
|
James Phone #: ###-####
|
BLD-Foundation | 7/24/2018 | 7/25/2018 | 7/25/2018 | A | PEND |
Dave Hannah
|
|
|
Ty Phone #: ###-#### this is a footing also mti will check rebar and test concrete setbacks and rebar ok
|
BLD-Foundation | 7/24/2018 | 7/24/2018 | 7/24/2018 | P | CANC |
Tony Young
|
|
|
Please call ahead // Ty Phone #: ###-#### Inspection cancelled from web by: Keeley Wilson
|