BLD-Final | 8/10/2018 | 8/13/2018 | 8/14/2018 | P | PASS |
Dave Hannah
|
|
|
Not on site, please call ahead so we can make sure the door is open for you and can meet you there. Scott Phone #: ###-#### Inspection requested via web by Scott Henderson ok after fire finals
|
FIRE-Final Inspection | 8/13/2018 | 8/14/2018 | 8/14/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, no fire alarm modifications, firee xtinguisher are placed with current inspection tags. Final life fire safety inspection for area of work complete.
Request for Fire Life Safety final. Not on site. Bldg is secure. Please call ahead so I can meet you there. Scott, ###-#### Inspection requested via web by Scott Henderson
|
BLD-Framing/Rough-in | 7/17/2018 | 7/18/2018 | 7/18/2018 | A | PASS |
Tony Young
|
|
|
Framing inspection for joist reinforcing that has been completed in the basement. Dustin Palmer will be onsite contact, ###-####. Phone #: ###-#### Inspection requested via web by Scott Henderson
|
BLD-Framing/Rough-in | 7/11/2018 | 7/12/2018 | 7/12/2018 | A | PASS |
Tony Young
|
|
|
For Stage Expansion framing. Phone #: ###-#### Inspection requested via web by Scott Henderson
|
BLD-Framing/Rough-in | 7/10/2018 | 7/11/2018 | 7/11/2018 | P | PEND |
Tony Young
|
|
|
For Stage Expansion framing. Phone #: ###-#### Inspection requested via web by Scott Henderson,, needs trades 1st
|
BLD-Framing/Rough-in | 7/10/2018 | 7/10/2018 | 7/10/2018 | P | NR |
Tony Young
|
|
|
For Stage Expansion framing. Phone #: ###-#### Inspection requested via web by Scott Henderson,, need trades,, add studs under single plate loads
|