BLD-Final | 4/1/2018 | 4/2/2018 | 4/2/2018 | P | PASS |
Tony Young
|
|
|
Elevation certificate complete- Jason Taylor to review All other inspections passed Phone #: ###-#### Inspection requested via web by Daniel Appel
|
DOC - Permit Finaled | 4/2/2018 | 4/2/2018 | 4/2/2018 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Wall cover | 1/25/2018 | 1/26/2018 | 1/26/2018 | P | PASS |
Tony Young
|
|
|
after 3 PM please Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Energy code compliance | 1/25/2018 | 1/26/2018 | 1/26/2018 | P | PASS |
Tony Young
|
|
|
after 3 PM please Phone #: ###-#### Inspection requested via web by Daniel Appel,, work in progress
|
BLD-Framing/Rough-in | 1/25/2018 | 1/26/2018 | 1/26/2018 | P | PASS |
Tony Young
|
|
|
after 3 PM please Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Other | 1/25/2018 | 1/25/2018 | 1/25/2018 | P | PASS |
Tony Young
|
|
|
Dan; Phone #: ###-####,, soffits
|
BLD-Framing/Rough-in | 1/24/2018 | 1/25/2018 | 1/25/2018 | A | PART |
Tony Young
|
|
|
Dan; Phone #: ###-####,, corrections,, ok to insulate
|
BLD-Framing/Rough-in | 1/23/2018 | 1/23/2018 | 1/23/2018 | P | NR |
Jim Sly
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel Need Mech approval.
|
BLD-Wall Bracing | 1/5/2018 | 1/8/2018 | 1/8/2018 | A | PASS |
Jim Sly
|
|
|
Dan Phone #: ###-#### Exterior shear nailing only......OK.
|
BLD-Foundation | 11/21/2017 | 11/22/2017 | 11/22/2017 | P | PART |
Tony Young
|
|
|
dane Phone #: ###-####
|
BLD-Foundation | 11/21/2017 | 11/22/2017 | 11/22/2017 | A | PART |
Tony Young
|
|
|
Dane Phone #: ###-####,, most rebar is in place
|
BLD-Foundation | 11/20/2017 | 11/21/2017 | 11/21/2017 | P | NR |
Tony Young
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 11/17/2017 | 11/20/2017 | 11/20/2017 | P | PART |
Tony Young
|
|
|
dane Phone #: ###-####,, setbacks appear ok,, work in progress
|
BLD-Footing | 11/14/2017 | 11/15/2017 | 11/15/2017 | P | NR |
Brandon Shaw
|
|
|
Dane Phone #: ###-####
|