BLD-Final | 3/13/2018 | 3/13/2018 | 3/13/2018 | P | PASS |
Dave Hannah
|
|
|
Dave, this needs finaled now that the shell and core is done so they can have permanent occupancy. Let me know if there are any problems. Thanks, Angie Brosious ###-####.
|
FIRE-Final Inspection | 3/13/2018 | 3/13/2018 | 3/13/2018 | P | PASS |
Jim Page
|
|
|
Final life fire safety inspection complete.
|
BLD-Aging Inspection | 2/14/2018 | 2/14/2018 | 2/20/2018 | | PEND |
Dave Hannah
|
|
|
|
BLD-Final | 12/6/2017 | 12/7/2017 | 12/7/2017 | A | PART |
Dave Hannah
|
|
|
WIll Phone #: ###-#### ok for temp occ ok for perm after bldg is signed off and other trades go perm and rest room sinks are finished
|
FIRE-Final Inspection | 12/6/2017 | 12/7/2017 | 12/7/2017 | A | PART |
Jim Page
|
|
|
Fire sprinkler inspection for area of work complete, fire alarm inspection for area of work complete, fire extinguishers are mounted with current inspection tags. Final life fire safety complete for area of work. Tenant space will remain in TCO status until core and shell is complete and finaled. Tenant space can be finaled when core and shell is complete and finaled.
|
BLD-Conference | 12/6/2017 | 12/6/2017 | 12/7/2017 | P | DONE |
Dave Hannah
|
|
|
Will Phone #: ###-####
|
BLD-Conference | 12/5/2017 | 12/5/2017 | 12/5/2017 | P | DONE |
Dave Hannah
|
|
|
Will Phone #: ###-####
|
FIRE-Conference | 12/4/2017 | 12/5/2017 | 12/5/2017 | A | DONE |
Jim Page
|
|
|
Fire conference complete.
|
BLD-Framing/Rough-in | 11/16/2017 | 11/17/2017 | 11/17/2017 | A | PASS |
Dave Hannah
|
|
|
rick Phone #: ###-####
|
BLD-Framing/Rough-in | 11/8/2017 | 11/9/2017 | 11/17/2017 | A | PEND |
Dave Hannah
|
|
|
Rick Phone #: ###-#### need engineering
|
BLD-Energy code compliance | 11/15/2017 | 11/15/2017 | 11/15/2017 | A | PASS |
Dave Hannah
|
|
|
perimeter insulation // Rick ###-####
|
BLD-Framing/Rough-in | 11/13/2017 | 11/13/2017 | 11/15/2017 | P | PART |
Dave Hannah
|
|
|
Rick Phone #: ###-#### need engineering on beam to beam conections the rest is ok
|
BLD-Energy code compliance | 11/13/2017 | 11/13/2017 | 11/15/2017 | P | CANC |
Dave Hannah
|
|
|
Rick Phone #: ###-####
|
BLD-Other | 11/14/2017 | 11/14/2017 | 11/15/2017 | P | CANC |
Dave Hannah
|
|
|
perimeter insulation // Rick ###-####
|
BLD-Framing/Rough-in | 11/8/2017 | 11/8/2017 | 11/9/2017 | P | PART |
Dave Hannah
|
|
|
Rick Phone #: ###-#### ok to inasulate ext walls need engineer to look at beam to beam connections and beam to coulmn connections
|
BLD-Framing/Rough-in | 10/3/2017 | 10/4/2017 | 10/4/2017 | A | PART |
Dave Hannah
|
|
|
Will Phone #: ###-#### ok to cover upper ceiling area
|