BLD-Final | 6/8/2018 | 6/11/2018 | 6/11/2018 | A | PASS |
Brandon Shaw
|
|
|
Ready to complete our Final for our Occupancy Permit. Will have our Hillside Approval letter from Public Works Monday morning. Please call with any issue''s. Thank you! Kim Phone #: ###-#### Inspection requested via web by Steve Hanson
|
DOC - Permit Finaled | 6/11/2018 | 6/11/2018 | 6/11/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 6/11/2018 | 6/11/2018 | 6/11/2018 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 3.5
|
BLD-Final | 5/31/2018 | 6/1/2018 | 6/1/2018 | P | PART |
Tony Young
|
|
|
Hi Tony, Per our conversation looking to have you inspect the house for completiin at 416 Sherman. Call with any questions. Thank you, Kim Phone #: ###-#### Inspection requested via web by Steve Hanson,, walk through,, needs hillside from public works, railing, window well ladder
|
BLD-Foundation | 4/16/2018 | 4/17/2018 | 4/17/2018 | P | PASS |
Jim Storey
|
|
|
Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro would like late afternoon rebar ok for wall se lot
|
BLD-Footing | 4/12/2018 | 4/13/2018 | 4/13/2018 | A | PASS |
Brandon Shaw
|
|
|
Retaining wall- driveway, SE side
|
BLD-Other | 2/22/2018 | 2/23/2018 | 2/23/2018 | A | PART |
Tony Young
|
|
|
soffit,, ok ,, work in progress
|
BLD-Wall cover | 2/21/2018 | 2/21/2018 | 2/21/2018 | P | PART |
Tony Young
|
|
|
Chris,, soffits; Phone #: ###-####,, wip on sheetrock layer,, ok
|
BLD-Energy code compliance | 2/14/2018 | 2/16/2018 | 2/16/2018 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson
|
BLD-Framing/Rough-in | 2/14/2018 | 2/15/2018 | 2/15/2018 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson,, still working on missed bearing on floor trusses,, ok to insulate
|
BLD-Wall Bracing | 2/14/2018 | 2/15/2018 | 2/15/2018 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson
|
BLD-Framing/Rough-in | 2/13/2018 | 2/14/2018 | 2/14/2018 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson,, work in proress
|
BLD-Wall Bracing | 2/13/2018 | 2/14/2018 | 2/14/2018 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson,, work in progress
|
BLD-Framing/Rough-in | 2/9/2018 | 2/12/2018 | 2/12/2018 | A | FAIL |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson,, c/n posted,, do not insulate
|
BLD-Wall Bracing | 2/9/2018 | 2/12/2018 | 2/12/2018 | A | FAIL |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson,, need to strap and nail portals
|
BLD-Wall Bracing | 2/1/2018 | 2/2/2018 | 2/2/2018 | A | FAIL |
Brandon Shaw
|
|
|
See correction notice-
|
BLD-Wall Bracing | 1/29/2018 | 1/30/2018 | 1/30/2018 | A | FAIL |
Tony Young
|
|
|
Thank you Phone #: ###-#### Inspection requested via web by Steve Hanson,, re-do shear,, need plans
|
BLD-Foundation | 11/16/2017 | 11/16/2017 | 11/17/2017 | P | DONE |
Dave Hannah
|
|
|
Anne Phone #: ###-####
|
BLD-Foundation | 11/17/2017 | 11/17/2017 | 11/17/2017 | A | PASS |
Dave Hannah
|
|
|
Anne Phone #: ###-####
|
BLD-Footing | 11/7/2017 | 11/7/2017 | 11/7/2017 | P | PART |
Tony Young
|
|
|
Annie Phone #: ###-####,, work in progress,, ok
|