BLD-Ceiling Grid Inspection | 4/20/2018 | 4/23/2018 | 4/23/2018 | A | PASS |
Dave Hannah
|
|
|
Area A and Exam rooms ceilings Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Energy code compliance | 2/16/2018 | 2/20/2018 | 2/20/2018 | A | PASS |
Dave Hannah
|
|
|
Jim Phone #: ###-#### ok to cover ext walls
|
BLD-Framing/Rough-in | 2/16/2018 | 2/20/2018 | 2/20/2018 | A | PART |
Dave Hannah
|
|
|
Jim Phone #: ###-#### areas A and B ok to cover ext walls ok
|
BLD-Final | 12/27/2017 | 12/28/2017 | 12/28/2017 | A | NR |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Ceiling Grid Inspection | 12/4/2017 | 12/4/2017 | 12/4/2017 | P | PASS |
Dave Hannah
|
|
|
Mechanical re-inspection scheduled for this afternoon as well. More seismic wires were needed on diffusers. Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Ceiling Grid Inspection | 11/29/2017 | 11/29/2017 | 11/29/2017 | A | NR |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Ceiling Grid Inspection | 11/10/2017 | 11/13/2017 | 11/13/2017 | A | PASS |
Dave Hannah
|
|
|
suspended gypsum board ceiling framing. IVF LaB Phone #: ###-#### Inspection requested via web by Jim Williams hard lid in ivs lab
|
BLD-Energy code compliance | 9/14/2017 | 9/15/2017 | 9/15/2017 | A | PASS |
Dave Hannah
|
|
|
Inspect insulation and vapor barrier for wall cover. Thanks Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Framing/Rough-in | 9/12/2017 | 9/12/2017 | 9/13/2017 | P | PASS |
Dave Hannah
|
|
|
Framing prior to exterior wall insulation. Phone #: ###-#### Inspection requested via web by Jim Williams ok to insulate
|