BLD-Final | 11/29/2017 | 11/29/2017 | 11/29/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Wells
|
DOC - Permit Finaled | 11/29/2017 | 11/29/2017 | 11/29/2017 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 11/22/2017 | 11/27/2017 | 11/27/2017 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Wells. Needs electrical final and install handrails.
|
BLD-Energy code compliance | 10/10/2017 | 10/10/2017 | 10/10/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Wells
|
BLD-Framing/Rough-in | 10/10/2017 | 10/10/2017 | 10/10/2017 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Wells
|
BLD-Framing/Rough-in | 10/9/2017 | 10/9/2017 | 10/9/2017 | P | DEFR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Wells. Will inspect on energy code.
|
BLD-Framing/Rough-in | 10/7/2017 | 10/9/2017 | 10/9/2017 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Wells. Foam seal complete. Still needs to correct hangar issues. Ok to insulate.
|
BLD-Framing/Rough-in | 10/5/2017 | 10/6/2017 | 10/6/2017 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tom Wells. Nail off simpson hangars in garage on LVL's. Provide correct hangars on 2 of the LVL's in the garage. Complete the airseal on plumbing penetrations on the main level. Correction notice issued. Ok to insulate.
|
BLD-Wall Bracing | 9/14/2017 | 9/15/2017 | 9/15/2017 | A | PASS |
Jim Sly
|
|
|
Shear // Zane Phone #: ###-####
|
BLD-Foundation | 8/31/2017 | 9/1/2017 | 9/1/2017 | A | PASS |
Jim Sly
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
BLD-Footing | 8/30/2017 | 8/31/2017 | 8/31/2017 | A | PASS |
Mike Jordan
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|