BLD-Final | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs. Ok for temp occ. Will be ok for perm occ. once zoning signs perm.
|
FIRE-Final Inspection | 6/26/2018 | 6/27/2018 | 6/27/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Phone #: ###-#### Inspection requested via web by David Scaggs
|
FIRE-Final Inspection | 6/25/2018 | 6/25/2018 | 6/25/2018 | P | FAIL |
Jim Page
|
|
|
Only 1 smoke detector in the unit 102 would sound when test buttons was pushed, smoke detectors in the units all need to sound when smoke detection audible is activated.
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Final | 6/25/2018 | 6/25/2018 | 6/25/2018 | P | NR |
Mike Jordan
|
|
|
Fire Final called in for PM as well. Phone #: ###-#### Inspection requested via web by David Scaggs. Needs fire/life/safety fialfirst.
|
FIRE-Final Inspection | 6/22/2018 | 6/22/2018 | 6/22/2018 | P | FAIL |
Troy Cobbley
|
|
|
102 smoke alarms did not ring back. 104 head under stairs issue.
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Energy code compliance | 3/9/2018 | 3/9/2018 | 3/9/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Framing/Rough-in | 3/6/2018 | 3/6/2018 | 3/6/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Wall Bracing | 2/28/2018 | 2/28/2018 | 2/28/2018 | A | PASS |
Mike Jordan
|
|
|
Inspection requested via web by Marty Short
|
BLD-Footing | 1/15/2018 | 1/16/2018 | 1/16/2018 | A | PASS |
Mike Jordan
|
|
|
Interior footings, concrete scheduled for 10am Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD-Energy code compliance | 1/1/2018 | 1/2/2018 | 1/2/2018 | A | PART |
Mike Jordan
|
|
|
Foundation insulation Phone #: ###-#### Inspection requested via web by Marty Short. Noted to contractor that prior to backfill operations, areas to be backfilled must be free of snow and ice and not be frozen. Baclfill materials also to not be frozen.
|
BLD-Foundation | 12/26/2017 | 12/27/2017 | 12/27/2017 | P | PASS |
Mike Jordan
|
|
|
Concrete scheduled for 1pm Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD-Footing | 12/20/2017 | 12/21/2017 | 12/21/2017 | P | PASS |
Mike Jordan
|
|
|
Concrete scheduled for 2pm Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD-Footing | 12/17/2017 | 12/18/2017 | 12/18/2017 | A | CANC |
Mike Jordan
|
|
|
Concrete scheduled for 12pm Phone #: ###-#### Inspection requested via web by Marty Short
|