BLD-Aging Inspection | 7/12/2018 | 7/12/2018 | 7/12/2018 | | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 2/28/2018 | 2/28/2018 | 2/28/2018 | P | PASS |
Mike Jordan
|
|
|
Kitchen walls Phone #: ###-#### Inspection requested via web by Andrew Clark
|
BLD-Energy code compliance | 2/15/2018 | 2/15/2018 | 2/15/2018 | P | PART |
Mike Jordan
|
|
|
Only need upstairs master bedroom addition inspected. We would like to start sheetrocking master bedroom. Phone #: ###-#### Inspection requested via web by Andrew Clark. Framing in master bedroom ok, pending mech rough in inspection for vent. fans. Also discussed hard wiring provisions for the smoke detectors.
|
BLD-Framing/Rough-in | 1/25/2018 | 1/26/2018 | 1/26/2018 | P | PASS |
Mike Jordan
|
|
|
We have new engineering for lvl beams. Phone #: ###-#### Inspection requested via web by Andrew Clark
|
BLD-Framing/Rough-in | 1/23/2018 | 1/23/2018 | 1/23/2018 | P | FAIL |
Brandon Shaw
|
|
|
Need mech rough in, Not as per plans- (3) 2x8 DF beams at front porch, (2) 5x9 Glue Lams at back porch with attachment bracket, LvLs used, instead- provide engineering and fastener schedule for as built.
|