BLD-Final | 9/26/2018 | 9/26/2018 | 9/26/2018 | P | PASS |
Mike Jordan
|
|
|
Call half hour before to meet // Mike Phone #: ###-####. All issues resolved. OK for perm occ.
|
BLD-Final | 6/27/2018 | 6/28/2018 | 6/28/2018 | P | PART |
Mike Jordan
|
|
|
I am at Albertson''s on Broadway, so please give a time frame on we you think you might be onsite, so i can head that way.Thanks Phone #: ###-#### Inspection requested via web by Mike Beeson. Ok for temp occ. Needs to provide ADA compliant service desk at main eneterance.
|
FIRE-Final Inspection | 6/27/2018 | 6/28/2018 | 6/28/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 6/13/2018 | 6/13/2018 | 6/13/2018 | P | FAIL |
Troy Cobbley
|
|
|
Remove the deadbolts from doors 102A and 119A and provide with single action, ADA compliant, hardware. Remove the exit sign in the Hallway that directs people to the Service Bays. Provide exit sign at door 102A as per sheet E2.0L. Remove all of the padlock haps.
Please contact Tim Toups at the phone number listed. Phone #: ###-#### Inspection requested via web by Philip Allen
|
FIRE-Conference | 5/11/2018 | 5/11/2018 | 5/11/2018 | P | DONE |
Troy Cobbley
|
|
|
I spoke with the project superintendant about several existing fire alarm notification devices being overspaced. These devices were outside of the project related fire alarm permit scope of work. The issues will need to be addressed prior to a life safety sign off since the building scope of work is an Request for Occupancy for the entire building.
|
BLD-Ceiling Grid Inspection | 4/11/2018 | 4/12/2018 | 4/12/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Framing/Rough-in | 3/8/2018 | 3/9/2018 | 3/9/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Beeson. hard lid framing ok.
|
BLD-Framing/Rough-in | 3/5/2018 | 3/6/2018 | 3/6/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Beeson
|