BLD-Final | 8/3/2018 | 8/6/2018 | 8/6/2018 | A | PASS |
Brandon Shaw
|
|
|
Micheal Phone #: ###-####
|
DOC - Permit Finaled | 8/6/2018 | 8/6/2018 | 8/6/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | PART |
Tony Young
|
|
|
Please call ahead for access - Mike Phone #: ###-####,, needs tempered glass,, hand rail to unfinished basement, etc.,, ok to move house hold items in
|
BLD-Conference | 5/10/2018 | 5/10/2018 | 5/10/2018 | P | PART |
Tony Young
|
|
|
Michael Phone #: ###-####,, stair/handrail ?s
|
BLD-Energy code compliance | 3/20/2018 | 3/20/2018 | 3/20/2018 | P | PASS |
Dave Hannah
|
|
|
Michael Phone #: ###-####
|
BLD-Framing/Rough-in | 3/15/2018 | 3/15/2018 | 3/15/2018 | P | PART |
Tony Young
|
|
|
Michael Phone #: ###-####,, needs fire placed passed,, see paint notes for corrections,, ok to insulate
|
BLD-Conference | 3/12/2018 | 3/13/2018 | 3/13/2018 | A | PASS |
Tony Young
|
|
|
call when on way // Michael Phone #: ###-####,, stair ?s,, ok
|
BLD-Wall Bracing | 2/7/2018 | 2/7/2018 | 2/7/2018 | P | PASS |
Brandon Shaw
|
|
|
Garage
Hold downs, at house and garage, to be installed before framing inspection
|
BLD-Conference | 2/6/2018 | 2/6/2018 | 2/6/2018 | P | DONE |
Dave Hannah
|
|
|
Michael Phone #: ###-#### or Brad ###-####
|
BLD-Wall Bracing | 1/31/2018 | 1/31/2018 | 1/31/2018 | P | PART |
Tony Young
|
|
|
Michael Phone #: ###-####,, need to see hold downs at frame inspection,, house exterior ok to cover
|
BLD-Wall Bracing | 1/30/2018 | 1/31/2018 | 1/31/2018 | A | NR |
Tony Young
|
|
|
Michael Phone #: ###-####
|
BLD-Wall Bracing | 1/30/2018 | 1/30/2018 | 1/30/2018 | P | NR |
Tony Young
|
|
|
Michael Phone #: ###-####
|
BLD-Foundation | 12/21/2017 | 12/21/2017 | 12/21/2017 | P | PASS |
Tony Young
|
|
|
Ryan-pour time 4:00 Phone #: ###-####
|
BLD-Footing | 12/19/2017 | 12/19/2017 | 12/19/2017 | P | PART |
Tony Young
|
|
|
Ryan Phone #: ###-####,, garage,, 3pm,, made 22' back up space,, per surveyer,, alley is 13.6'
|
BLD-Footing | 12/18/2017 | 12/19/2017 | 12/19/2017 | A | NR |
Tony Young
|
|
|
Ryan Phone #: ###-####
|
BLD-Foundation | 11/14/2017 | 11/14/2017 | 11/14/2017 | P | PART |
Tony Young
|
|
|
Ryan Phone #: ###-####,, basement wall,, work in progress
|
BLD-Footing | 11/8/2017 | 11/9/2017 | 11/9/2017 | A | PART |
Tony Young
|
|
|
Ryan Phone #: ###-####,, basement footings ok
|