BLD-Final | 3/25/2020 | 3/25/2020 | 3/25/2020 | P | PASS |
Dave Hannah
|
|
|
Tim Phone #: ###-####
|
FIRE-Final Inspection | 3/18/2020 | 3/19/2020 | 3/19/2020 | A | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection complete, signature card not available at time of inspection.
Tim Phone #: ###-####
|
FIRE-Final Inspection | 3/18/2020 | 3/18/2020 | 3/18/2020 | P | FAIL |
Jim Page
|
|
|
Fire riser room is not a rated room as required by Boise Municipal Code, Chapter 7 Fire Prevention Code section 903.1.2. Provide building permit fire review comments for project, documents are required to be onsite, per conversation with point of contact they are not onsite. Install addressing that is compliant with 2016 IFC section 505, current addressing does not meet the requirements of section 505. Provide corner lot addressing as defined in the BMC Chapter 7 section 505.3. Provide fire extinguishers with current inspection tags for each unit, fire extingiushers can be mounted under the sink. Correct the addressing with the monitoring company.
Tim Phone #: ###-####
|
BLD-Conference | 3/9/2020 | 3/10/2020 | 3/10/2020 | A | CANC |
Dave Hannah
|
|
|
Tim Phone #: ###-####
|
BLD-Final | 3/10/2020 | 3/10/2020 | 3/10/2020 | P | NR |
Dave Hannah
|
|
|
Tim Phone #: ###-####
|
BLD-Aging Inspection | 2/13/2020 | 2/13/2020 | 2/19/2020 | | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 2/12/2020 | 2/12/2020 | 2/19/2020 | | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 10/1/2019 | 10/1/2019 | 10/1/2019 | P | PASS |
Dave Hannah
|
|
|
Tim Phone #: ###-#### this finishs this blg for energy ok to cover
|
BLD-Energy code compliance | 9/24/2019 | 9/24/2019 | 9/24/2019 | A | PASS |
Dave Hannah
|
|
|
|
BLD-Wall cover | 9/23/2019 | 9/23/2019 | 9/24/2019 | P | PASS |
Dave Hannah
|
|
|
Tim Phone #: ###-####
|
BLD-Framing/Rough-in | 9/4/2019 | 9/4/2019 | 9/4/2019 | P | PASS |
Dave Hannah
|
|
|
Tim Phone #: ###-####
|
BLD-Foundation | 4/25/2019 | 4/25/2019 | 4/26/2019 | P | PASS |
Dave Hannah
|
|
|
Tim Phone #: ###-#### third floor center walls ok
|
BLD-Foundation | 4/15/2019 | 4/15/2019 | 4/16/2019 | P | PART |
Dave Hannah
|
|
|
Tim Phone #: ###-#### third floor ext wallsok
|
BLD-Foundation | 2/28/2019 | 2/28/2019 | 2/28/2019 | P | CANC |
Brandon Shaw
|
|
|
Tim Phone #: ###-####
|
BLD-Foundation | 2/19/2019 | 2/19/2019 | 2/19/2019 | P | PART |
Dave Hannah
|
|
|
Tim Phone #: ###-#### second floor int walls
|
BLD-Foundation | 1/28/2019 | 1/28/2019 | 1/28/2019 | P | PART |
Dave Hannah
|
|
|
Tim Phone #: ###-#### second level ext walls ok
|
BLD-Footing | 12/20/2018 | 12/21/2018 | 12/21/2018 | A | PASS |
Dave Hannah
|
|
|
Tim Phone #: ###-####
|
BLD-Foundation | 12/19/2018 | 12/20/2018 | 12/20/2018 | A | PASS |
Dave Hannah
|
|
|
wall-tim Phone #: ###-####
|
BLD-Foundation | 11/28/2018 | 11/28/2018 | 11/28/2018 | P | PART |
Dave Hannah
|
|
|
Wall-Tim Phone #: ###-#### second lift ok to place
|
BLD-Foundation | 10/16/2018 | 10/16/2018 | 10/16/2018 | P | PASS |
Mike Jordan
|
|
|
Tim-pour time 3:30 Phone #: ###-####
|
BLD-Foundation | 10/11/2018 | 10/11/2018 | 10/11/2018 | P | PASS |
Dave Hannah
|
|
|
Tim Phone #: ###-####
|
BLD-Footing | 10/2/2018 | 10/2/2018 | 10/2/2018 | P | PASS |
Dave Hannah
|
|
|
tim Phone #: ###-####
|