BLD-Final | 3/12/2018 | 3/16/2018 | 3/16/2018 | A | PASS |
Dave Hannah
|
|
|
Final C of O inspection. Key is in the exterior power outlet to the left of the detached garage man door. Thank you, steve Phone #: ###-#### Inspection requested via web by steve hanson
|
DOC - Permit Finaled | 3/16/2018 | 3/16/2018 | 3/16/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 12/14/2017 | 12/15/2017 | 12/15/2017 | A | PASS |
Tony Young
|
|
|
Energy compliance and insulation inspection for approval to cover. Thanks, steve Phone #: ###-#### Inspection requested via web by steve hanson
|
BLD-Energy code compliance | 12/12/2017 | 12/14/2017 | 12/14/2017 | P | PART |
Tony Young
|
|
|
Energy compliance and insulation inspection for approval to cover. Thanks, steve Phone #: ###-#### Inspection requested via web by steve hanson,, correction posted
|
BLD-Framing/Rough-in | 12/9/2017 | 12/12/2017 | 12/12/2017 | P | PASS |
Dave Hannah
|
|
|
Plans are on site under the stairs. Thank you, steve Phone #: ###-#### Inspection requested via web by steve hanson
|
BLD-Framing/Rough-in | 12/7/2017 | 12/11/2017 | 12/9/2017 | P | CANC |
Tony Young
|
|
|
Frame Inspection. Shear fix for master bedroom wall has been completed. Engineering is on site. If you would like an electronic copy please let me know. thanks, steve Phone #: ###-#### >> Inspection requested via web by steve hanson Inspection cancelled from web by: steve hanson
|
BLD-Wall Bracing | 11/17/2017 | 11/17/2017 | 11/17/2017 | P | PART |
Tony Young
|
|
|
Shear inspection please. Thank you, steve Phone #: ###-#### Inspection requested via web by steve hanson,, need to have revised engineering for change in window layout on north side of home affecting the hold down locations,, ok to cover exterior after finishing the nailing
|
BLD-Foundation | 10/25/2017 | 10/25/2017 | 10/25/2017 | P | PASS |
Tony Young
|
|
|
Phone #: ###-####
|
BLD-Foundation | 10/24/2017 | 10/25/2017 | 10/25/2017 | A | PASS |
Tony Young
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
BLD-Footing | 10/23/2017 | 10/24/2017 | 10/24/2017 | P | PART |
Tony Young
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo ,, work in progress..
|
BLD-Conference | 10/17/2017 | 10/17/2017 | 10/17/2017 | A | DEFR |
Tony Young
|
|
|
EROSION CONTROL site review needed prior to dig. Thank you, steve Phone #: ###-#### Inspection requested via web by steve hanson
|