BLD-Final | 12/17/2018 | 12/18/2018 | 12/18/2018 | A | PASS |
Mike Jordan
|
|
|
Tony Phone #: ###-####. OK for perm occ.
|
BLD-Final | 12/13/2018 | 12/14/2018 | 12/14/2018 | A | NR |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Needs both mech. permits finaled first.
|
BLD-Final | 11/14/2018 | 11/15/2018 | 11/15/2018 | P | PASS |
Mike Jordan
|
|
|
Tony Phone #: ###-####. OK for temp occ. Will be ok for perm occ. once trades sign perm.
|
FIRE-Final Inspection | 11/14/2018 | 11/15/2018 | 11/15/2018 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
Tony Phone #: ###-####
|
FIRE-Final Inspection | 11/13/2018 | 11/14/2018 | 11/14/2018 | P | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to final when the project related fire alarm and fire sprinkler permit is addressed.
Tony Phone #: ###-####
|
BLD-Final | 11/14/2018 | 11/14/2018 | 11/14/2018 | A | FAIL |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Provide code compliant hardware on west stair.
|
FIRE-Conference | 11/7/2018 | 11/7/2018 | 11/7/2018 | P | DONE |
Troy Cobbley
|
|
|
I verified exit light and emergency light function
|
BLD-Ceiling Grid Inspection | 10/18/2018 | 10/18/2018 | 10/18/2018 | P | PASS |
Mike Jordan
|
|
|
Ceiling grid for soffits in ware house ok.
|
BLD-Ceiling Grid Inspection | 10/17/2018 | 10/18/2018 | 10/18/2018 | A | CANC |
Mike Jordan
|
|
|
Jose Phone #: ###-####.
|
BLD-Ceiling Grid Inspection | 10/3/2018 | 10/3/2018 | 10/3/2018 | P | PASS |
Jim Storey
|
|
|
Jose Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/27/2018 | 9/27/2018 | 9/27/2018 | P | PASS |
Mike Jordan
|
|
|
Jose Phone #: ###-####. 1st. Floor only ok, pending sprinkler rough in.
|
BLD-Ceiling Grid Inspection | 9/25/2018 | 9/26/2018 | 9/27/2018 | A | CANC |
Mike Jordan
|
|
|
Jose Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/26/2018 | 9/26/2018 | 9/27/2018 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Other | 8/6/2018 | 8/7/2018 | 8/7/2018 | A | CANC |
Mike Jordan
|
|
|
Jose-plenum wall Phone #: ###-####
|
BLD-Energy code compliance | 8/2/2018 | 8/2/2018 | 8/2/2018 | P | PASS |
Mike Jordan
|
|
|
Jose Phone #: ###-####. 2nd.floor ok.
|
BLD-Energy code compliance | 7/30/2018 | 7/31/2018 | 7/31/2018 | A | PASS |
Mike Jordan
|
|
|
Jose Phone #: ###-####. Exterior walls, north of gridline 2 only, 1st. floor.
|
BLD-Framing/Rough-in | 7/31/2018 | 7/31/2018 | 7/31/2018 | A | PART |
Mike Jordan
|
|
|
Jose Phone #: ###-####. Interior steel stud framed walls, 1st. and 2nd. floors north of gridline 2. pending plumbing rough in inspection.
|
BLD-Framing/Rough-in | 7/12/2018 | 7/13/2018 | 7/13/2018 | A | PART |
Mike Jordan
|
|
|
Jose Phone #: ###-####. Interior steel stud framed walls from gridlines 2 to 5 ok. Pending plumbing rough in inspection. Also noted that a select number of the interior full height walls are to be plenum walls. Electrical and plumbing inspectors were notified, as there are additional requirements.
|
BLD-Framing/Rough-in | 6/22/2018 | 6/25/2018 | 6/26/2018 | A | PASS |
Mike Jordan
|
|
|
Jose Phone #: ###-####. Exterior steel stud columns ok.
|
BLD-Footing | 3/12/2018 | 3/13/2018 | 3/13/2018 | A | PART |
Mike Jordan
|
|
|
Jose Phone #: ###-####. Interior column pad footings and exterior perimter footings. Pending special inspection.
|