BLD-Final | 11/30/2017 | 11/30/2017 | 11/30/2017 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 11/30/2017 | 11/30/2017 | 11/30/2017 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, life fire safety inspection for area of work passed/complete.
|
FIRE-Final Inspection | 11/3/2017 | 11/6/2017 | 11/6/2017 | A | PART |
Jim Page
|
|
|
No fire alarm modifications, fire extinguishers are in common areas with current inspection tags. TCO for life fire safety is authorized for 30 days per conversation with Scott Arellano, TCO is contingent on the fire sprinkler modifications being completed. Once fire sprinkler work is completed then life fire safey can be finaled.
|
BLD-Final | 11/3/2017 | 11/6/2017 | 11/6/2017 | P | PART |
Jim Storey
|
|
|
30 heads up please- Garret Phone #: ###-#### tco ok FYI – See below regarding TCO on BLD17-03697 if that is all that is remaining.
Jason
|
FIRE-Final Inspection | 11/2/2017 | 11/2/2017 | 11/2/2017 | P | FAIL |
Troy Cobbley
|
|
|
The existing sprinkler pendants are overspaced in atleast four locations and will need modified. I also noted that I would need to verify the hardware on the two new doors when installed. The annual inspection for the sprinkler system is current.
|
BLD-Framing/Rough-in | 11/1/2017 | 11/2/2017 | 11/2/2017 | A | PASS |
Jim Storey
|
|
|
call 30 min ahead // Garrett Phone #: ###-####
|
BLD-Framing/Rough-in | 11/1/2017 | 11/1/2017 | 11/1/2017 | P | DEFR |
Jim Storey
|
|
|
call 30 min ahead // Garrett Phone #: ###-####
|