BLD-Final | 2/1/2018 | 2/1/2018 | 2/1/2018 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Beeson
|
DOC - Permit Finaled | 2/1/2018 | 2/1/2018 | 2/1/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 1/30/2018 | 1/31/2018 | 2/1/2018 | P | PEND |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Beeson ok for temp occ
|
FIRE-Final Inspection | 1/29/2018 | 1/30/2018 | 1/30/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags, thumb-turn function for deadbolts on restroom doors has been made inoperable. Final life fire safety inspection for area of work complete.
|
FIRE-Final Inspection | 1/26/2018 | 1/26/2018 | 1/26/2018 | A | FAIL |
Jim Page
|
|
|
Door holder magnets were not in place at time of inspection. Doors/door hardware were not installed on restroom doors at time of inspection. Fire alarms did not work correctly for final inspection which resulted in a failed inspection.
|
FIRE-Final Inspection | 1/24/2018 | 1/24/2018 | 1/24/2018 | P | FAIL |
Jim Page
|
|
|
Project attached permits for fire alarm and fire sprinkler needs to be inspected and finaled before life fire safety inspection can be performed.
|
BLD-Ceiling Grid Inspection | 1/18/2018 | 1/19/2018 | 1/19/2018 | A | PASS |
Dave Hannah
|
|
|
Please call when you are heading this way, Thanks Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Framing/Rough-in | 1/12/2018 | 1/12/2018 | 1/12/2018 | A | PASS |
Dave Hannah
|
|
|
We got a UL rated drawing from the Architect on those columns. Please call Jake at ###-#### and he can meet you with a printed copy. Everything is wrapped with 2 layers and the ones on the west wall has three layers on the face. Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Framing/Rough-in | 1/10/2018 | 1/11/2018 | 1/12/2018 | P | PASS |
Dave Hannah
|
|
|
Jake is on site during the day. Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Framing/Rough-in | 1/7/2018 | 1/8/2018 | 1/8/2018 | A | PART |
Dave Hannah
|
|
|
Restroom framing, all backing is done in fire treated lumber. Phone #: ###-#### Inspection requested via web by Mike Beeson ok to insulate and cover all but for around colunms colunms need fire proofing
|
BLD-Framing/Rough-in | 1/2/2018 | 1/3/2018 | 1/3/2018 | A | PASS |
Dave Hannah
|
|
|
Framing at lobby entry to Ballroom Phone #: ###-#### Inspection requested via web by Mike Beeson
|
BLD-Framing/Rough-in | 12/27/2017 | 12/27/2017 | 12/27/2017 | P | PART |
Dave Hannah
|
|
|
Framing inspection, Mike Beeson Phone #: ###-#### Inspection requested via web by Mike Beeson bottom of sofits
|