BLD-Final | 4/27/2018 | 4/27/2018 | 4/27/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
DOC - Permit Finaled | 4/27/2018 | 4/27/2018 | 4/27/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 4/21/2018 | 4/24/2018 | 4/24/2018 | A | NR |
Mike Jordan
|
|
|
Garage door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle. Everything ok. Needs mech final first prior to sign off.
|
BLD-Energy code compliance | 3/8/2018 | 3/8/2018 | 3/8/2018 | A | PASS |
Brandon Shaw
|
|
|
OK to cover
|
BLD-Energy code compliance | 3/6/2018 | 3/7/2018 | 3/7/2018 | P | FAIL |
Brandon Shaw
|
|
|
See framing notes- add additional fasteners to BG2 (2 ply) Truss-
|
BLD-Framing/Rough-in | 3/6/2018 | 3/6/2018 | 3/6/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Ok to insulate. provide additional fasteners at bottom chord og BG2 in garage.
|
BLD-Wall Bracing | 2/13/2018 | 2/14/2018 | 2/14/2018 | P | PASS |
Mike Jordan
|
|
|
Fortino Phone #: ###-####
|
BLD-Foundation | 1/25/2018 | 1/26/2018 | 1/26/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Foundation | 1/24/2018 | 1/25/2018 | 1/25/2018 | P | CANC |
Mike Jordan
|
|
|
Dane Phone #: ###-####. No one on site. No foundation forms erected.
|
BLD-Foundation | 1/23/2018 | 1/24/2018 | 1/24/2018 | P | NR |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Foundation | 1/22/2018 | 1/23/2018 | 1/23/2018 | P | NR |
Mike Jordan
|
|
|
Dane Phone #: ###-####. No one on site. No stemwall forms erected.
|
BLD-Footing | 1/19/2018 | 1/22/2018 | 1/22/2018 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 1/18/2018 | 1/19/2018 | 1/19/2018 | P | FAIL |
Mike Jordan
|
|
|
Dane Phone #: ###-####. Contractor to compact pitrun. Appears to be uncontrolled fill.
|