Permit Information
Permit NumberBLD17-03890
StatusFinaled
Name HARDING HOMES INC
Site Address 2628 W NEFF ST
Project NameL3B1 Odom Estates
Customer Number 
ePlanReviewYes
Description
Permit for the construction of a new 2404 sq. ft., two story (first story 1048 sq. ft., second story 1356 sq. ft.) single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately ### sq. ft. of covered patio/porch and a 579 sq. ft. attached garage per the approved plans. R-1C zoning and setbacks per planning. MDH
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/23/20191/24/20191/24/2019PPASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by James Jackson
DOC - Permit Finaled1/24/20191/24/20191/24/2019PPASS
DetailsBrandon Shaw
BLD-Blower Door Test Results1/24/20191/24/20191/24/2019PDONE
DetailsBrandon Shaw
ACH50- 4.6
BLD-Final1/17/20191/18/20191/18/2019AFAIL
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by James Jackson. Provide handrail at main entry exterior stairs.
BLD-Energy code compliance11/1/201811/9/201811/8/2018ADONE
DetailsTony Young
Phone #: ###-#### Inspection requested via web by James Jackson
BLD-Energy code compliance11/2/201811/2/201811/2/2018PPASS
DetailsTony Young
BLD-Other11/1/201811/1/201811/1/2018PPASS
DetailsTony Young
We will have insulators on site today so that you can see the baffels we are installing. Phone #: ###-#### Inspection requested via web by James Jackson
BLD-Conference11/1/201811/1/201811/1/2018PPASS
DetailsTony Young
Insulators are onsite now so that you can see the baffels. Let me know when you will be there and I will meet you to discuss. Phone #: ###-#### Inspection requested via web by James Jackson
BLD-Conference11/1/201811/1/201811/1/2018ADEFR
DetailsTony Young
We will have insulators on site today so that you can see the baffels we are installing. Phone #: ###-#### Inspection requested via web by James Jackson,, not ready
BLD-Framing/Rough-in10/29/201810/30/201810/30/2018APASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by James Jackson
BLD-Framing/Rough-in10/25/201810/25/201810/25/2018PFAIL
DetailsTony Young
Phone #: ###-#### Inspection requested via web by James Jackson,, correction posted,, strap beams/plates, add king studs per plan, fire blocks, seal plate at vac line, nail king studs into header layers, justify how the roof will be vented, fireblock stair run where no sheetrock will be on the underside, nail plywood by the top of stairs,, will need a level landing out exit door,, do not insulate
BLD-Wall Bracing10/5/201810/8/201810/8/2018APART
DetailsBrandon Shaw
Work in progress- hold downs and floor to floor straps
BLD-Foundation8/31/20188/31/20188/31/2018PPART
DetailsTony Young
gilber Phone #: ###-####,, work in progress,, needs rebar clearance to forms,, ok after fixes
BLD-Footing8/28/20188/29/20188/29/2018APASS
DetailsDave Hannah
Gilbert Phone #: ###-####