BLD-Final | 12/6/2019 | 12/9/2019 | 12/9/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Bob Thornton
|
DOC - Permit Finaled | 12/9/2019 | 12/9/2019 | 12/9/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 10/22/2018 | 10/22/2018 | 10/22/2018 | P | PEND |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Bob Thornton. Needs special inspection final letter.
|
FIRE-Final Inspection | 10/18/2018 | 10/19/2018 | 10/19/2018 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
Phone #: ###-#### Inspection requested via web by Bob Thornton
|
FIRE-Final Inspection | 10/17/2018 | 10/18/2018 | 10/18/2018 | A | PART |
Troy Cobbley
|
|
|
Life safety complete for the second floor. All emergency lights and exit signs have been repaired. Can't final the permit until the sprinkler permit is complete which is providing sprinkler protection at the ground level, at the stairs.
Phone #: ###-#### Inspection requested via web by Bob Thornton
|
FIRE-Final Inspection | 9/26/2018 | 9/28/2018 | 9/28/2018 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was for the second floor. Need all exit signs and emergency lights for the entire facility repaired and the fire extinguishers provided with annual inspection.
Please call when you are on your way. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
FIRE-Final Inspection | 9/26/2018 | 9/26/2018 | 9/26/2018 | P | CANC |
Troy Cobbley
|
|
|
Call me when you head this way. Phone #: ###-#### >> Inspection requested via web by Bob Thornton Inspection cancelled from web by: Bob Thornton
|
BLD-Framing/Rough-in | 6/29/2018 | 6/29/2018 | 6/29/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Bob Thornton. @nd. floor interior steel stud framed walls ok.
|
BLD-Footing | 5/1/2018 | 5/2/2018 | 5/2/2018 | A | PASS |
Mike Jordan
|
|
|
We have concrete scheduled for 10 AM Phone #: ###-#### Inspection requested via web by Bob Thornton. Interior column pad footing for new column at mezz. addition.
|