BLD-Final | 10/4/2018 | 10/5/2018 | 10/5/2018 | A | PASS |
Dave Hannah
|
|
|
zack Phone #: ###-####
|
FIRE-Final Inspection | 10/3/2018 | 10/4/2018 | 10/4/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire exitnguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete.
zack Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/24/2018 | 9/25/2018 | 9/25/2018 | A | PASS |
Dave Hannah
|
|
|
Zack Phone #: ###-####
|
BLD-Final | 9/7/2018 | 9/10/2018 | 9/10/2018 | A | PART |
Dave Hannah
|
|
|
Zack Phone #: ###-#### phase one ok
|
FIRE-Final Inspection | 9/7/2018 | 9/7/2018 | 9/7/2018 | P | PART |
Jim Page
|
|
|
Project is being worked in phases, fire sprinklers complete for phase 2 (West side of level 7), fire alarms complete for phase 2, fire extinguisher are placed with current inspection tags, final life fire safety inspection for phase 2 west side complete, west side to be inspected at a later date.
Zack Phone #: ###-####
|
BLD-Framing/Rough-in | 8/30/2018 | 8/31/2018 | 8/31/2018 | A | PART |
Tony Young
|
|
|
rocky Phone #: ###-####,, walls ok pending trades
|
BLD-Final | 8/17/2018 | 8/20/2018 | 8/20/2018 | P | PART |
Dave Hannah
|
|
|
partial pednding MEC & PLM - Zack Phone #: ###-#### phase 1 ok to occ
|
BLD-Ceiling Grid Inspection | 8/10/2018 | 8/13/2018 | 8/13/2018 | A | PASS |
Dave Hannah
|
|
|
Zack Phone #: ###-####
|
FIRE-Final Inspection | 8/10/2018 | 8/10/2018 | 8/10/2018 | P | PART |
Jim Page
|
|
|
Project is being worked in phases, fire sprinklers complete for phase 1 (East side of level 7), fire alarms complete for phase 1, fire extinguisher are placed with current inspection tags, final life fire safety inspection for phase 1 east side complete, west side to be inspected at a later date.
Final life safety // Zac Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/3/2018 | 8/3/2018 | 8/3/2018 | P | PASS |
Dave Hannah
|
|
|
Zack Phone #: ###-####
|
BLD-Framing/Rough-in | 8/2/2018 | 8/3/2018 | 8/3/2018 | A | PASS |
Dave Hannah
|
|
|
Zach Phone #: ###-####
|
BLD-Framing/Rough-in | 5/7/2018 | 5/8/2018 | 5/8/2018 | A | PART |
Dave Hannah
|
|
|
Ken Phone #: ###-####k to cover first phase
|
BLD-Framing/Rough-in | 5/7/2018 | 5/7/2018 | 5/7/2018 | P | NR |
Tony Young
|
|
|
Ken Phone #: ###-####
|