BLD-Final | 6/20/2019 | 6/20/2019 | 6/20/2019 | P | PASS |
Mike Jordan
|
|
|
jeff Phone #: ###-####. Ok for perm occ. All issues resolved.
|
BLD-Final | 5/10/2019 | 5/13/2019 | 5/13/2019 | A | PART |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Ok for temp oc. Need final letter from special inspection agency and needs to lower sinks in bathrroms to meet ADA.
|
FIRE-Final Inspection | 5/3/2019 | 5/6/2019 | 5/6/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractor is going to provide an occupant load sign for the Conference room prior to a building inspection.
Jeff Phone #: ###-####
|
FIRE-Final Inspection | 5/1/2019 | 5/2/2019 | 5/2/2019 | P | CANC |
Mark Scharfen
|
|
|
Alarmco not ready. Jeff Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 4/24/2019 | 4/24/2019 | 4/24/2019 | P | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
BLD-Concrete | 4/15/2019 | 4/16/2019 | 4/16/2019 | A | PASS |
Mike Jordan
|
|
|
Jeff- concrete pad inspection Phone #: ###-####. Exterior slab on grade for trash enclosure.
|
BLD-Conference | 3/8/2019 | 3/11/2019 | 3/11/2019 | A | DONE |
Mike Jordan
|
|
|
Jeff Phone #: ###-####-3190
|
BLD-Footing | 2/28/2019 | 3/1/2019 | 3/1/2019 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Footings have been excavated down to 24 inch min depth.
|
BLD-Footing | 2/27/2019 | 2/28/2019 | 2/28/2019 | P | NR |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Footings at mid landing need min 24 inch for frost depth.
|
BLD-Ceiling Grid Inspection | 2/22/2019 | 2/25/2019 | 2/25/2019 | A | NR |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Needs trades first.
|
BLD-Framing/Rough-in | 1/30/2019 | 1/31/2019 | 1/31/2019 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Interior framing for new vestibule ok.
|
BLD-Footing | 1/11/2019 | 1/14/2019 | 1/14/2019 | P | CANC |
Mike Jordan
|
|
|
Jeff Phone #: ###-#### // cancelled by requestor 1-11-2019 GF
|
BLD-Framing/Rough-in | 1/10/2019 | 1/11/2019 | 1/11/2019 | P | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Riser room framing ok.
|
BLD-Framing/Rough-in | 1/9/2019 | 1/9/2019 | 1/9/2019 | P | PART |
Brandon Shaw
|
|
|
Mezzanine bathroom and IT room... Beam to Beam straps, as per plans...
|
BLD-Framing/Rough-in | 1/7/2019 | 1/8/2019 | 1/8/2019 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Interior wwod and steel stud framed walls at 1st. floor only and remaining shear walls.
|
BLD-Framing/Rough-in | 12/18/2018 | 12/19/2018 | 12/19/2018 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Interior steel stud framed walls from floor to ceiling and mezz to ceiling on gridline E grids 4.5 to 9 and grids 4.5 from grids A to E. per approved plans and ASI 02 for top track connection to purlins.
|
BLD-Framing/Rough-in | 12/13/2018 | 12/14/2018 | 12/14/2018 | A | PART |
Mike Jordan
|
|
|
new exterior wall framing for new exterior finish. partial 2nd floor deck diaphragm. Waiting on on panel edge nailing.
|
BLD-Conference | 12/13/2018 | 12/13/2018 | 12/13/2018 | P | DONE |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 11/20/2018 | 11/21/2018 | 11/21/2018 | A | PASS |
Mike Jordan
|
|
|
Jeff Webber Phone #: ###-####. at channel on interior side of exterior walls ok.
|
BLD-Framing/Rough-in | 11/19/2018 | 11/20/2018 | 11/20/2018 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Shear walls on grids A and 9.
|
BLD-Conference | 11/9/2018 | 11/13/2018 | 11/13/2018 | A | DONE |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Discussed one siding shear walls prior to standing were walls are against the existing structure.
|