BLD-Aging Inspection | 10/14/2019 | 10/14/2019 | 10/16/2019 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 8/13/2019 | 8/13/2019 | 8/15/2019 | | PASS |
Jim Storey
|
|
|
zoning temp.
|
BLD-Final | 6/13/2019 | 6/13/2019 | 6/13/2019 | P | PASS |
Jim Storey
|
|
|
issues resolved. re-inspection for Building final Phone #: ###-#### Inspection requested via web by J.C. Murray final ok
|
BLD-Final | 6/11/2019 | 6/12/2019 | 6/12/2019 | P | NR |
Jim Storey
|
|
|
Building final. Phone #: ###-#### Inspection requested via web by J.C. Murray need handrail 12 inches top and bottom// under stair protection.
|
BLD-Final | 6/11/2019 | 6/11/2019 | 6/11/2019 | P | NR |
Jim Storey
|
|
|
Building final. Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Final | 5/30/2019 | 5/31/2019 | 5/31/2019 | P | NR |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by J.C. Murray
|
FIRE-Final Inspection | 5/30/2019 | 5/31/2019 | 5/31/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire al;arm inspection complete, fire extinguishers are placed with current inspection tags, knox box is located by fire sprinkler riser room. Final life fire safety inspection complete, fire alarms must be monitored after occupancy.
Fire / Life ; Safety Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Ceiling Grid Inspection | 2/14/2019 | 2/14/2019 | 2/14/2019 | P | PASS |
Jim Storey
|
|
|
Building B south 12 units. drop ceiling for cover. fire caulking. Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Wall cover | 2/1/2019 | 2/1/2019 | 2/1/2019 | P | PASS |
Jim Storey
|
|
|
Building B - north 12 units. drop ceiling for cover, fire caulking. Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Energy code compliance | 1/10/2019 | 1/11/2019 | 1/11/2019 | A | PASS |
Mike Jordan
|
|
|
Bld B - south 12 energy, insulation and tenting. Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Framing/Rough-in | 12/28/2018 | 12/28/2018 | 12/28/2018 | P | PASS |
Jim Storey
|
|
|
Bld B - south 12 fire caulking/ framing Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Energy code compliance | 12/28/2018 | 12/28/2018 | 12/28/2018 | P | PASS |
Jim Storey
|
|
|
Bld -B: north 12 units. insulation and RC Channel Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Framing/Rough-in | 12/21/2018 | 12/21/2018 | 12/21/2018 | P | PASS |
Jim Storey
|
|
|
Bld B - north 12 unit framing and fire caulking. Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Framing/Rough-in | 12/6/2018 | 12/7/2018 | 12/7/2018 | P | PASS |
Jim Storey
|
|
|
Bld B - interior framing and fire caulking Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Framing/Rough-in | 11/14/2018 | 11/15/2018 | 11/15/2018 | A | PASS |
Jim Storey
|
|
|
Bld B - roof truss engineering Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Framing/Rough-in | 11/13/2018 | 11/14/2018 | 11/14/2018 | A | PART |
Jim Storey
|
|
|
Bld B - roof truss engineering and interior framing. Phone #: ###-#### Inspection requested via web by J.C. Murray no engineering
|
BLD-Framing/Rough-in | 11/12/2018 | 11/13/2018 | 11/13/2018 | A | CANC |
Jim Sly
|
|
|
Bld B rough framing interior, truss engineering . Phone #: ###-#### Inspection requested via web by J.C. Murray Called in wrong Bldg.
|
BLD-Framing/Rough-in | 11/6/2018 | 11/7/2018 | 11/7/2018 | A | PASS |
Jim Storey
|
|
|
Building B. exterior nailing, straps Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Framing/Rough-in | 11/1/2018 | 11/2/2018 | 11/2/2018 | A | PASS |
Jim Storey
|
|
|
Bld B; foundation to building anchor bolts, hold downs and titan bolts. Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Framing/Rough-in | 9/14/2018 | 9/19/2018 | 9/19/2018 | A | PASS |
Jim Storey
|
|
|
slab on grade shear walls, center and south sections.
Building B Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Framing/Rough-in | 9/4/2018 | 9/5/2018 | 9/5/2018 | P | PART |
Jim Sly
|
|
|
partial 1st floor shear wall north end. Bld B. Inspection requested via web by J.C. Murray Interior layers.....OK.
|
BLD-Foundation | 7/25/2018 | 7/25/2018 | 7/25/2018 | P | PASS |
Jim Storey
|
|
|
Manual Phone #: ###-####
|
BLD-Footing | 7/20/2018 | 7/20/2018 | 7/20/2018 | P | PASS |
Jim Storey
|
|
|
manuel Phone #: ###-####
|