BLD-Final | 10/22/2018 | 10/23/2018 | 10/23/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 10/23/2018 | 10/23/2018 | 10/23/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 10/23/2018 | 10/23/2018 | 10/23/2018 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4.23
|
BLD-Energy code compliance | 8/23/2018 | 8/23/2018 | 8/23/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 8/20/2018 | 8/20/2018 | 8/20/2018 | P | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
OK to insulate
|
BLD-Framing/Rough-in | 8/16/2018 | 8/16/2018 | 8/16/2018 | P | FAIL |
Brandon Shaw
|
|
|
Need foam/air seal... Beams and support girders to bear down to foundation as per plans... Squash blocks required for point load at support girder... Hold downs to be installed per manufactures installation instructions... Fire blocking needed at gas line chase...
|
BLD-Wall Bracing | 8/3/2018 | 8/3/2018 | 8/3/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Foundation | 4/17/2018 | 4/17/2018 | 4/17/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 4/16/2018 | 4/16/2018 | 4/16/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|