FIRE-Final Inspection | 6/24/2020 | 6/26/2020 | 6/26/2020 | A | FAIL |
Troy Cobbley
|
|
|
Provide plan mods showing the actual new door locations and actual door swing direction, provide sprinkler and fire alarm modifications (permits) for the required changes due to the new wall installations.
screened // Dustin Phone #: ###-####
|
BLD-Framing/Rough-in | 6/18/2020 | 6/19/2020 | 6/19/2020 | A | PASS |
Mike Jordan
|
|
|
screened // Destin Phone #: ###-####. Framing appears to be done per the approved plans. Mech and elec. issues resolved. needs to call in for fire/life/safety final.
|
BLD-Framing/Rough-in | 2/26/2020 | 2/27/2020 | 2/27/2020 | A | FAIL |
Mike Jordan
|
|
|
Nicole Phone #: ###-####. All work has been completed with no inspections. Appears that electrical work was done as well. Will need to provide the city approved set of plans and small docs. Will need to set up conferances with electrical and fire inspectors as well.
|
Extend Permit 90/180 days | | 2/3/2020 | 2/3/2020 | | DONE |
Joe Bruce
|
|
|
Extended permit (2) two 180 day extensions per email from contractor, Destin Reid w/ D&F Constructors
|