Permit Information
Permit NumberBLD18-00632
StatusFinaled
Name JORDAN WILCOMB CONSTRUCTION
Site Address 9492 W EMERALD ST
Project NameSalvation Army
Customer NumberBLD17-04447
ePlanReview 
Description
*(SALVATION ARMY) Permit for a new 15,406 sq.ft., 1 story building of type V-B construction. This facility will include a, gym/community center, classrooms, kitchen, and offices. This building is required to be fully fire sprinklered and includes a fire alarm system. Separate fire sprinkler and fire alarm permits will be required for the required fire protection systems; as regulated by the Fire Department. CDM/SJA
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/24/20199/25/20199/25/2019APASS
DetailsMike Jordan
Jim Phone #: ###-####. OK for perm occ.
FIRE-Final Inspection9/23/20199/24/20199/24/2019PPASS
DetailsTroy Cobbley
Life safety passed. Jim Phone #: ###-####
FIRE-Final Inspection9/23/20199/23/20199/23/2019PCANC
DetailsTroy Cobbley
Need the FIR inspection for the range hoods scheduled/passed. Jim Phone #: ###-####
FIRE-Final Inspection9/18/20199/19/20199/19/2019AFAIL
DetailsTroy Cobbley
Previous correctlons have been addressed but additional permits are required for the residential type 1 hood extinguishing systems. Jim Phone #: ###-####
FIRE-Final Inspection9/11/20199/12/20199/12/2019PFAIL
DetailsJim Page
FIR permits for hood suppression and fire alarm need to be finaled before life fire safety can be signed as complete. Provice internally illuminated exit signage and emergency lighting on exterior gates. Fire caulk condensate drain hole in riser room, riser room is a 1 hour rated assembly. Escutcheon in level 1 common restroom does not cover the entire sprinkler hole, escutcheon must cover entire hole. Remove masking from sprinkler heads in level 2 janitors closet and mech room.

Jim Phone #: ###-####
BLD-Conference9/11/20199/12/20199/12/2019ACANC
DetailsBrandon Shaw
Jim Phone #: ###-####
BLD-Ceiling Grid Inspection7/25/20197/25/20197/25/2019APART
DetailsTell Riley
//ok to cover all grid//kitchen area not ready//trades passed rough in for grid cover//
BLD-Framing/Rough-in5/7/20195/8/20195/8/2019APASS
DetailsMike Jordan
Hi Mike,,, west single story hard lids for cover
Phone #: ###-#### Inspection requested via web by Jim Carriveau
BLD-Energy code compliance4/22/20194/22/20194/22/2019APASS
DetailsMike Jordan
Hello Mike
west single story, exterior wall insulation for cover Phone #: ###-#### Inspection requested via web by Jim Carriveau
BLD-Framing/Rough-in4/22/20194/22/20194/22/2019APASS
DetailsMike Jordan
Hello Mike
west single story, exterior wall insulation for cover Phone #: ###-#### Inspection requested via web by Jim Carriveau. Interior steel stud framed walls ok.
BLD-Framing/Rough-in1/29/20191/30/20191/30/2019APASS
DetailsMike Jordan
Hello Michael, looking for framing inspection to proceed with exterior drywall west single story Phone #: ###-#### Inspection requested via web by Jim Carriveau. Exterior steel stud framing ok to sheet exterior side.
BLD-Framing/Rough-in1/24/20191/25/20191/25/2019APASS
DetailsMike Jordan
Hi Mike, looking to drywall roof parapet of west single story Phone #: ###-#### Inspection requested via web by Jim Carriveau. West single story parapet ok for cover.
BLD-Foundation7/13/20187/13/20187/13/2018APASS
DetailsMike Jordan
Hi Mike
we have a 12:00 placement scheduled for the west structure, all stem walls. Strata will be onsite for rebar and concrete testing. Phone #: ###-#### Inspection requested via web by Jim Carriveau. perimeter and interior stemwalls for west structure(gym and school)
BLD-Other7/3/20187/6/20187/6/2018PPART
DetailsJim Sly
late friday please // rebar insp // Doug Phone #: ###-####
3:32 pm No one on site. Called Doug. This will be the 2nd Footing pour. STRATA has been on site, and will be on site Very Early Monday am. when they pour.