BLD-Final | 9/24/2019 | 9/25/2019 | 9/25/2019 | A | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. OK for perm occ.
|
FIRE-Final Inspection | 9/23/2019 | 9/24/2019 | 9/24/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Jim Phone #: ###-####
|
FIRE-Final Inspection | 9/23/2019 | 9/23/2019 | 9/23/2019 | P | CANC |
Troy Cobbley
|
|
|
Need the FIR inspection for the range hoods scheduled/passed. Jim Phone #: ###-####
|
FIRE-Final Inspection | 9/18/2019 | 9/19/2019 | 9/19/2019 | A | FAIL |
Troy Cobbley
|
|
|
Previous correctlons have been addressed but additional permits are required for the residential type 1 hood extinguishing systems. Jim Phone #: ###-####
|
FIRE-Final Inspection | 9/11/2019 | 9/12/2019 | 9/12/2019 | P | FAIL |
Jim Page
|
|
|
FIR permits for hood suppression and fire alarm need to be finaled before life fire safety can be signed as complete. Provice internally illuminated exit signage and emergency lighting on exterior gates. Fire caulk condensate drain hole in riser room, riser room is a 1 hour rated assembly. Escutcheon in level 1 common restroom does not cover the entire sprinkler hole, escutcheon must cover entire hole. Remove masking from sprinkler heads in level 2 janitors closet and mech room.
Jim Phone #: ###-####
|
BLD-Conference | 9/11/2019 | 9/12/2019 | 9/12/2019 | A | CANC |
Brandon Shaw
|
|
|
Jim Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/25/2019 | 7/25/2019 | 7/25/2019 | A | PART |
Tell Riley
|
|
|
//ok to cover all grid//kitchen area not ready//trades passed rough in for grid cover//
|
BLD-Framing/Rough-in | 5/7/2019 | 5/8/2019 | 5/8/2019 | A | PASS |
Mike Jordan
|
|
|
Hi Mike,,, west single story hard lids for cover Phone #: ###-#### Inspection requested via web by Jim Carriveau
|
BLD-Energy code compliance | 4/22/2019 | 4/22/2019 | 4/22/2019 | A | PASS |
Mike Jordan
|
|
|
Hello Mike west single story, exterior wall insulation for cover Phone #: ###-#### Inspection requested via web by Jim Carriveau
|
BLD-Framing/Rough-in | 4/22/2019 | 4/22/2019 | 4/22/2019 | A | PASS |
Mike Jordan
|
|
|
Hello Mike west single story, exterior wall insulation for cover Phone #: ###-#### Inspection requested via web by Jim Carriveau. Interior steel stud framed walls ok.
|
BLD-Framing/Rough-in | 1/29/2019 | 1/30/2019 | 1/30/2019 | A | PASS |
Mike Jordan
|
|
|
Hello Michael, looking for framing inspection to proceed with exterior drywall west single story Phone #: ###-#### Inspection requested via web by Jim Carriveau. Exterior steel stud framing ok to sheet exterior side.
|
BLD-Framing/Rough-in | 1/24/2019 | 1/25/2019 | 1/25/2019 | A | PASS |
Mike Jordan
|
|
|
Hi Mike, looking to drywall roof parapet of west single story Phone #: ###-#### Inspection requested via web by Jim Carriveau. West single story parapet ok for cover.
|
BLD-Foundation | 7/13/2018 | 7/13/2018 | 7/13/2018 | A | PASS |
Mike Jordan
|
|
|
Hi Mike we have a 12:00 placement scheduled for the west structure, all stem walls. Strata will be onsite for rebar and concrete testing. Phone #: ###-#### Inspection requested via web by Jim Carriveau. perimeter and interior stemwalls for west structure(gym and school)
|
BLD-Other | 7/3/2018 | 7/6/2018 | 7/6/2018 | P | PART |
Jim Sly
|
|
|
late friday please // rebar insp // Doug Phone #: ###-#### 3:32 pm No one on site. Called Doug. This will be the 2nd Footing pour. STRATA has been on site, and will be on site Very Early Monday am. when they pour.
|