BLD-Final | 9/16/2019 | 9/17/2019 | 9/17/2019 | A | PASS |
Tony Young
|
|
|
Call Chris when you are on your way. Phone #: ###-#### Inspection requested via web by Clayton Conner
|
DOC - Permit Finaled | 9/17/2019 | 9/17/2019 | 9/17/2019 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 9/16/2019 | 9/16/2019 | 9/17/2019 | P | DEFR |
Dave Hannah
|
|
|
Call Chris when you are on your way. Phone #: ###-#### Inspection requested via web by Clayton Conner
|
BLD-Final | 8/21/2019 | 8/21/2019 | 8/22/2019 | P | PEND |
Tony Young
|
|
|
Final Inspection Phone #: ###-#### Inspection requested via web by Clayton Conner on site walk through,, working on stairs
|
BLD-Final | 8/12/2019 | 8/13/2019 | 8/21/2019 | A | PEND |
Tony Young
|
|
|
Final Inspection Phone #: ###-#### Inspection requested via web by Clayton Conner
|
BLD-Final | 8/9/2019 | 8/12/2019 | 8/12/2019 | P | DEFR |
Tony Young
|
|
|
Final Inspection Phone #: ###-#### Inspection requested via web by Clayton Conner
|
BLD-Conference | 8/8/2019 | 8/9/2019 | 8/9/2019 | A | PART |
Tony Young
|
|
|
Clayton Phone #: ###-####,, walk through for final,, needs, hillside PW approval, guard rail interior, letter of approval on cable guard rails, general other items
|
BLD-Other | 3/11/2019 | 3/12/2019 | 3/12/2019 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Clayton Conner,, soffits,, work in progress,, ok
|
BLD-Energy code compliance | 3/8/2019 | 3/11/2019 | 3/11/2019 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Clayton Conner,, soffits are also work in progress
|
BLD-Energy code compliance | 3/7/2019 | 3/8/2019 | 3/8/2019 | A | NR |
Tony Young
|
|
|
Insulation Inspection. Phone #: ###-#### Inspection requested via web by Clayton Conner
|
BLD-Framing/Rough-in | 3/7/2019 | 3/8/2019 | 3/8/2019 | A | PASS |
Tony Young
|
|
|
Framing - WUI and Soffit Phone #: ###-#### Inspection requested via web by Clayton Conner
|
BLD-Framing/Rough-in | 2/5/2019 | 2/5/2019 | 2/5/2019 | P | PART |
Tony Young
|
|
|
Approved plan is in trailer. Please call or text first. Thanks! Phone #: ###-#### Inspection requested via web by Clayton Conner,, needs interior shear in some areas,, needs some areas sealed,, ok to insulate
|
BLD-Framing/Rough-in | 2/1/2019 | 2/1/2019 | 2/1/2019 | P | NR |
Tony Young
|
|
|
Caulk and seal and partial framing for cover. Need to finish two walls of shear on the inside and then framing inspection should be set. Please call before hand as approved plans are locked in trailer. Thank you, Clayton Conner Phone #: ###-#### Inspection requested via web by Clayton Conner,, walk through part only
|
BLD-Energy code compliance | 2/1/2019 | 2/1/2019 | 2/1/2019 | A | PART |
Tony Young
|
|
|
Caulk and seal and partial framing for cover. Need to finish two walls of shear on the inside and then framing inspection should be set. Please call before hand as approved plans are locked in trailer. Thank you, Clayton Conner Phone #: ###-#### Inspection requested via web by Clayton Conner,, foam seal ok after minor fixes,, frame not ready,, partial walk through only
|
BLD-Wall Bracing | 11/20/2018 | 11/20/2018 | 11/20/2018 | P | PART |
Tony Young
|
|
|
Mike will be on site. Call if you need me to come out. Thank you, Clayton. Phone #: ###-#### Inspection requested via web by Clayton Conner,, exterior ok,, verify hold downs at frame and interior shear
|
BLD-Wall Bracing | 11/19/2018 | 11/20/2018 | 11/20/2018 | A | NR |
Tony Young
|
|
|
Mike will be on site. Call if you need me to come out. Thank you, Clayton. Phone #: ###-#### Inspection requested via web by Clayton Conner
|
BLD-Foundation | 9/14/2018 | 9/14/2018 | 9/14/2018 | P | PASS |
Dave Hannah
|
|
|
retaining walls // Alvaro Phone #: ###-####
|
BLD-Footing | 9/4/2018 | 9/4/2018 | 9/5/2018 | P | PART |
Brandon Shaw
|
|
|
Retaining wall
|
BLD-Footing | 8/7/2018 | 8/8/2018 | 8/8/2018 | A | PASS |
Mike Jordan
|
|
|
Cal Phone #: ###-####. Garage footings.
|
BLD-Foundation | 7/13/2018 | 7/13/2018 | 7/13/2018 | P | PART |
Tony Young
|
|
|
Cale Phone #: ###-####,, work in progress,, ok
|
BLD-Footing | 5/30/2018 | 5/30/2018 | 5/30/2018 | P | PART |
Tony Young
|
|
|
Pouring today about 2:30 please have Tony call if there are any problems. Phone #: ###-#### Inspection requested via web by Clayton Conner,, work in progress
|