BLD-Final | 5/11/2020 | 5/12/2020 | 5/12/2020 | A | PASS |
Brandon Shaw
|
|
|
*screened* Please call ahead for access, looking to have both Jim & Brandon at same time - Bill Phone #: ###-####
|
DOC - Permit Finaled | 5/12/2020 | 5/12/2020 | 5/12/2020 | P | PASS |
Brandon Shaw
|
|
|
|
FIRE-Final Inspection | 5/11/2020 | 5/12/2020 | 5/12/2020 | A | PASS |
Jim Page
|
|
|
Final life fire safety inspection for scope of work is complete, signature card not available at time of inspection.
*screened* Please call ahead for access, looking to have both Jim & Brandon at same time - Bill Phone #: ###-####
|
BLD-Aging Inspection | 12/26/2019 | 12/26/2019 | 12/26/2019 | | CANC |
Brandon Shaw
|
|
|
|
BLD-Aging Inspection | 12/25/2019 | 12/25/2019 | 12/26/2019 | | CANC |
Brandon Shaw
|
|
|
|
BLD-Aging Inspection | 8/13/2019 | 8/13/2019 | 8/13/2019 | | PASS |
Brandon Shaw
|
|
|
|
BLD-Aging Inspection | 3/29/2019 | 3/29/2019 | 4/1/2019 | | PASS |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 11/15/2018 | 11/15/2018 | 11/15/2018 | P | PART |
Dave Hannah
|
|
|
Call if any questions on location // John Phone #: ###-#### three offices south end ok to cover after elec rough in
|
BLD-Ceiling Grid Inspection | 11/15/2018 | 11/15/2018 | 11/15/2018 | P | NR |
Dave Hannah
|
|
|
Call if any questions on location // John Phone #: ###-#### remove screws from top trace of into grid move lights and get elec rough ins
|
BLD-Final | 8/13/2018 | 8/14/2018 | 8/14/2018 | A | PART |
Jim Storey
|
|
|
Bill-wants Temp C of O Phone #: ###-#### 1st phase ok
|
FIRE-Final Inspection | 8/13/2018 | 8/13/2018 | 8/13/2018 | P | PART |
Jim Page
|
|
|
Fire life safety inspection for phase 1 complete.
Bill Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/18/2018 | 7/19/2018 | 7/19/2018 | A | PASS |
Mike Jordan
|
|
|
Bill Phone #: ###-####. Grid ok, pending fire sprinkler rough in inspection.
|
BLD-Framing/Rough-in | 6/12/2018 | 6/13/2018 | 6/13/2018 | A | PASS |
Jim Storey
|
|
|
Bill Phone #: ###-####
|