BLD-Final | 3/8/2019 | 3/11/2019 | 3/11/2019 | A | PASS |
Jim Storey
|
|
|
Kevin Phone #: ###-####
|
DOC - Permit Finaled | 3/11/2019 | 3/11/2019 | 3/11/2019 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 1/16/2019 | 1/16/2019 | 1/16/2019 | P | PASS |
Jim Storey
|
|
|
Please call Kevin Phone #: ###-#### Inspection requested via web by Chris Fuhrman 2nd phase of occ ok for new caffiteria use. exting ok
|
BLD-Final | 1/14/2019 | 1/15/2019 | 1/15/2019 | P | NR |
Jim Storey
|
|
|
Please call Kevin Phone #: ###-#### Inspection requested via web by Chris Fuhrman c/n signage to indcate exits/remove debri and workers/ handrail required at srair.
|
FIRE-Final Inspection | 1/14/2019 | 1/15/2019 | 1/15/2019 | A | PART |
Jim Page
|
|
|
Life fire safety inspection for TCO of cafeteria expansion complete.
Please call Kevin Phone #: ###-#### Inspection requested via web by Chris Fuhrman
|
BLD-Final | 1/11/2019 | 1/14/2019 | 1/14/2019 | P | NR |
Jim Storey
|
|
|
Kevin Phone #: ###-####
|
FIRE-Final Inspection | 1/11/2019 | 1/14/2019 | 1/14/2019 | P | FAIL |
Jim Page
|
|
|
Spoke with fire alarm contractor, in duct detectors on RTU's suppling main open area are not hooked to fire panel, FIR permit for fire alarms needs to be finaled before life fire safety inspection.
Kevin Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 1/11/2019 | 1/11/2019 | 1/11/2019 | P | PASS |
Jim Storey
|
|
|
Kevin Phone #: ###-#### ceilling in kitchen ok exit path being maintaned.
|
BLD-Framing/Rough-in | 1/10/2019 | 1/10/2019 | 1/10/2019 | P | PASS |
Jim Storey
|
|
|
Please call Kevin; Firewall Phone #: ###-#### Inspection requested via web by Chris Fuhrman south 2 hr wall complet ok to cover.
|
BLD-Framing/Rough-in | 1/7/2019 | 1/8/2019 | 1/8/2019 | P | PART |
Jim Storey
|
|
|
Kevin Phone #: ###-#### 3/4 height of core borad installed with ch studs// need stager of core board aprox 15 to 16 ft.
|
BLD-Wall Bracing | 12/17/2018 | 12/18/2018 | 12/18/2018 | A | PASS |
Mike Jordan
|
|
|
Kevin-interior wall inspection Phone #: ###-####. Interior steel stud framed walls ok.
|
BLD-Energy code compliance | 12/10/2018 | 12/10/2018 | 12/10/2018 | P | PASS |
Mike Jordan
|
|
|
Kevin Phone #: ###-####. Exterior walls only ok.
|
BLD-Framing/Rough-in | 12/10/2018 | 12/10/2018 | 12/10/2018 | P | PASS |
Mike Jordan
|
|
|
Kevin Phone #: ###-####. Soffit framing around accordian doors ok.
|
BLD-Energy code compliance | 12/7/2018 | 12/10/2018 | 12/10/2018 | A | NR |
Mike Jordan
|
|
|
Kevin Phone #: ###-####. Moved to pm inspection.
|
BLD-Framing/Rough-in | 11/15/2018 | 11/15/2018 | 11/15/2018 | P | PASS |
Jim Storey
|
|
|
Kevin Phone #: ###-#### exterior walls north stair need 2hr assembly
|
BLD-Foundation | 8/31/2018 | 9/4/2018 | 9/4/2018 | A | PASS |
Jim Storey
|
|
|
Kevin Phone #: ###-#### walls ok / south ft/ ok with foam wrap around duct bank per engineer.
|
BLD-Foundation | 8/23/2018 | 8/28/2018 | 8/28/2018 | A | PART |
Jim Storey
|
|
|
rebar- Kevin Phone #: ###-#### south ft si to insp. corect bar to grade clearances
|
BLD-Foundation | 8/1/2018 | 8/1/2018 | 8/1/2018 | P | PASS |
Jim Storey
|
|
|
Kevin Phone #: ###-#### rebar ok pending si report
|
BLD-Footing | 7/25/2018 | 7/26/2018 | 7/26/2018 | P | PASS |
Jim Storey
|
|
|
Kevin Phone #: ###-####
|
BLD-Foundation | 7/18/2018 | 7/18/2018 | 7/18/2018 | P | PASS |
Jim Storey
|
|
|
Kevin Phone #: ###-#### center sec wall rebar ok
|
BLD-Foundation | 7/12/2018 | 7/13/2018 | 7/13/2018 | A | PASS |
Jim Storey
|
|
|
Kevin Phone #: ###-#### north sec
|
BLD-Footing | 7/11/2018 | 7/11/2018 | 7/11/2018 | P | PART |
Jim Storey
|
|
|
Kevin Phone #: ###-#### revise reinforced concrete footing detail above & adjacent to the 24in storm drain line to support & transfer the load from the building column above the pipe insp performed with si pending report
|
BLD-Foundation | 6/29/2018 | 7/2/2018 | 7/2/2018 | A | PART |
Dave Hannah
|
|
|
Kevin--late morning preferred, concrete at 12, special inspector on site Phone #: ###-#### 24 inch storm drain is rapped with 4inchs of foam ok to back fill spec inspection will finish rebar inspection.
|
BLD-Footing | 6/21/2018 | 6/22/2018 | 6/22/2018 | A | FAIL |
Jim Storey
|
|
|
Kevin Phone #: ###-#### col direct on top of large pipe not allowed per plan resubmit to city// north rebar less than 3 inches to grade//flood ft sillt need conpaction re tested or aproved by engineer.
|