BLD-Final | 9/18/2019 | 9/19/2019 | 9/19/2019 | A | PASS |
Tell Riley
|
|
|
Russ Phone #: ###-####//final is complete//landscaping is done//public works signed off//no sign off sheet onsite//
|
BLD-Aging Inspection | 9/16/2019 | 9/16/2019 | 9/16/2019 | | PASS |
Tell Riley
|
|
|
working on landscaping
|
BLD-Final | 7/15/2019 | 7/15/2019 | 7/15/2019 | P | PART |
Tell Riley
|
|
|
Troy is here now. Phone #: ###-#### Inspection requested via web by Russell Valline//temp Occupancy ok//needs landscape complete and public works sign offs//
|
FIRE-Final Inspection | 7/15/2019 | 7/15/2019 | 7/15/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety is passed.. Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Framing/Rough-in | 4/6/2019 | 4/8/2019 | 4/9/2019 | P | PART |
Jim Sly
|
|
|
enter on west side of the Building please see Russ thank you. Phone #: ###-#### Inspection requested via web by Russell Valline Framing....hard lid ceilings ....Locker rooms....plus......
|
BLD-Final | 3/21/2019 | 3/22/2019 | 3/22/2019 | A | PART |
Dave Hannah
|
|
|
come late morning we have fire in morning also thank you. Phone #: ###-#### Inspection requested via web by Russell Valline kitchen and lunch room area ok for temp occ
|
FIRE-Final Inspection | 3/21/2019 | 3/22/2019 | 3/22/2019 | A | PART |
Troy Cobbley
|
|
|
Life safety passed for Phase 1.
Inspection requested via web by Russell Valline
|
BLD-Final | 3/20/2019 | 3/21/2019 | 3/21/2019 | P | NR |
Jim Sly
|
|
|
Please come a little later Jim working on other inspections all day thanks Inspection requested via web by Russell Valline Need to have Ron Hills Letter for Phased Occupancy on site for next inspection. Need Fire Temp. Occ. approval.
|
FIRE-Final Inspection | 3/20/2019 | 3/21/2019 | 3/21/2019 | P | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm, fire sprinkler and hood suppression permits addressed. Need occupant load signs as discussed and fire dept access signage for the parking lot on the north side of the new building. Neeed determination of ADA requirements for the manual pull for the hood suppression system.
Please try to come early afternoon working on other inspections.
thanks s Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Ceiling Grid Inspection | 3/17/2019 | 3/18/2019 | 3/18/2019 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Russell Valline,, cloud in lunch room,, storage for kitchen, entry ok after trades are passed
|
FIRE-Conference | 3/17/2019 | 3/18/2019 | 3/18/2019 | A | DONE |
Troy Cobbley
|
|
|
I went over general life safety items with Russell. There were no small documents on site. Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Ceiling Grid Inspection | 3/4/2019 | 3/5/2019 | 3/5/2019 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Conference | 2/25/2019 | 2/26/2019 | 2/26/2019 | A | DONE |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Russell Valline
|
FIRE-Conference | 2/25/2019 | 2/26/2019 | 2/26/2019 | A | DONE |
Troy Cobbley
|
|
|
Russel and I spoke about temp. occupancy requirements and exit paths. I deferred him to Ron Hill in project management. Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Framing/Rough-in | 2/11/2019 | 2/12/2019 | 2/12/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Russell Valline kitchen/caff.cooller/closets/restarmms/hall/mez surround framing ok ceillings ok
|
BLD-Concrete | 9/13/2018 | 9/14/2018 | 9/14/2018 | P | PASS |
Jim Storey
|
|
|
We are grouting our first lift tomorrow if you wanted to see. grout truck will be here at 2:00 All west will be here testing and inspecting. Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Foundation | 8/20/2018 | 8/21/2018 | 8/21/2018 | P | PASS |
Jim Sly
|
|
|
All West is the Third party inspctor Phone #: ###-#### Inspection requested via web by Russell Valline OK pending Allwest special inspections,tests and approvals.
|
FIRE-Final Inspection | 8/14/2018 | 8/17/2018 | 8/17/2018 | P | PART |
Jim Page
|
|
|
Final life fire safety inspection for remodeled parking lot complete.
This is for the parking lot only Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Conference | 7/26/2018 | 7/27/2018 | 7/30/2018 | P | DONE |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD-Footing | 7/26/2018 | 7/27/2018 | 7/30/2018 | P | DONE |
Jim Sly
|
|
|
These are interior footings we do have Allwest 3rd party inspection also Inspection requested via web by Russell Valline OK pending Allwest special inspections, tests and approvals.
|
BLD-Foundation | 7/20/2018 | 7/23/2018 | 7/23/2018 | A | PASS |
Jim Sly
|
|
|
Jim just talk to you about this job and you explained as long Phone #: ###-#### Inspection requested via web by Russell Valline OK pending Allwest special inspections tests and approvals.
|
BLD-Footing | 7/12/2018 | 7/13/2018 | 7/13/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Russell Valline OK......pending Allwest special inspections, tests and approvals.
|
BLD-Footing | 7/11/2018 | 7/13/2018 | 7/12/2018 | A | NR |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Russell Valline Allwest will be special inspection.
|