BLD-Final | 4/11/2019 | 4/11/2019 | 4/11/2019 | P | PASS |
Mike Jordan
|
|
|
Per conversation with Mike Jordan yesterday, zoning and life safety finals were required prior to this building final. Zoning was passed by Katelyn Menuge yesterday (4/10). Life safety was passed by Troy Cobbley this morning (4/11). Phone #: ###-#### Inspection requested via web by Brian Asa
|
DOC - Permit Finaled | 4/11/2019 | 4/11/2019 | 4/11/2019 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 4/10/2019 | 4/11/2019 | 4/11/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Brain Phone #: ###-####
|
BLD-Final | 4/10/2019 | 4/10/2019 | 4/10/2019 | P | NR |
Mike Jordan
|
|
|
Contractor not onsite. Card not onsite. All work was completed and we were waiting for final fire prior to closing out this permit. That is finally complete. Please final/close out this permit at your earliest convenience. Thank you! Phone #: ###-#### Inspection requested via web by Brian Asa. Needs zoning and life/safety finals first. Brian Asa was contacted and made aware of outstanding items.
|
BLD-Conference | 8/23/2018 | 8/24/2018 | 8/24/2018 | A | CANC |
Mike Jordan
|
|
|
As early as possible Phone #: 3603148130 >> Inspection requested via mobile web by Coty
|
BLD-Framing/Rough-in | 8/24/2018 | 8/24/2018 | 8/24/2018 | A | PASS |
Mike Jordan
|
|
|
As early as possible Phone #: 3603148130 >> Inspection requested via mobile web by Coty. Framing for tower ok. Needs electrical permit and rough in inspections.
|
BLD-Framing/Rough-in | 8/22/2018 | 8/23/2018 | 8/23/2018 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Wall Bracing | 8/23/2018 | 8/23/2018 | 8/23/2018 | A | PASS |
Mike Jordan
|
|
|
Exterior sheathing is ok to cover.
|
BLD-Framing/Rough-in | 8/21/2018 | 8/22/2018 | 8/22/2018 | A | NR |
Mike Jordan
|
|
|
As early as possible Phone #: 3603148130 >> Inspection requested via mobile web by Coty
|
BLD-Footing | 8/10/2018 | 8/13/2018 | 8/13/2018 | A | PART |
Mike Jordan
|
|
|
As early as possible Phone #: 7028066033 >> Inspection requested via mobile web by Ted Nowak. Spoke with engineer and got clarification on footing reinforcement. Special inspector on site. Contractor will complete rebar and have special inspection.
|
BLD-Framing/Rough-in | 8/13/2018 | 8/13/2018 | 8/13/2018 | A | PART |
Mike Jordan
|
|
|
As early as possible Phone #: 7028066033 >> Inspection requested via mobile web by Ted Nowak. Interior straps and holddowns ok.
|
BLD-Concrete | 8/9/2018 | 8/10/2018 | 8/10/2018 | A | CANC |
Mike Jordan
|
|
|
Phone #: 3603148130 >> Inspection requested via mobile web by Coty
|
BLD-Footing | 8/9/2018 | 8/10/2018 | 8/10/2018 | A | FAIL |
Mike Jordan
|
|
|
Phone #: 3603148130 >> Inspection requested via mobile web by Coty. Miising #5 at 10 inches on center from existing footing. Needs special inspection for epoxy.
|
BLD-Framing/Rough-in | 8/2/2018 | 8/7/2018 | 8/7/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: 7028066033 >> Inspection requested via mobile web by Ted Nowak. Interior wood framed half walls and window infills.
|
BLD-Conference | 7/31/2018 | 8/1/2018 | 8/1/2018 | A | DONE |
Mike Jordan
|
|
|
Phone #: 7028066033 >> Inspection requested via mobile web by Ted Nowak. reviewed plans, scope of work and job schedule with contractor.
|