BLD-Final | 11/13/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Becker OK for Perm Occ.
|
FIRE-Final Inspection | 11/13/2018 | 11/15/2018 | 11/15/2018 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractro agreed to provide ADA hardware on the pocket door and provide sticker at the main exit door with the keyed egress hardware.
Mark Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/8/2018 | 11/8/2018 | 11/8/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Becker
|
BLD-Ceiling Grid Inspection | 11/6/2018 | 11/8/2018 | 11/8/2018 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mark Becker Inspection cancelled from web by: Mark Becker
|
BLD-Ceiling Grid Inspection | 10/31/2018 | 10/31/2018 | 10/31/2018 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Becker. Draft stop ok. Needs MEP's sign off prior to installing tile and another grid inspction.
|
BLD-Wall cover | 10/12/2018 | 10/12/2018 | 10/12/2018 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Becker. Draft stop has been installled, but has several gaps. Will verify completion at grid inspection.
|
BLD-Framing/Rough-in | 10/4/2018 | 10/5/2018 | 10/5/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Becker. Interior steel studframed walls ok. No grid at this time. Pending electrical rough in inspection.
|
BLD-Framing/Rough-in | 9/18/2018 | 9/19/2018 | 9/19/2018 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Becker
|
BLD-Conference | 9/19/2018 | 9/19/2018 | 9/19/2018 | A | DONE |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Mark Becker
|
BLD-Framing/Rough-in | 9/18/2018 | 9/18/2018 | 9/18/2018 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mark Becker Inspection cancelled from web by: Mark Becker
|