BLD-Final | 12/13/2018 | 12/14/2018 | 12/14/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Erik Wylie
|
DOC - Permit Finaled | 12/14/2018 | 12/14/2018 | 12/14/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Blower Door Test Results | 12/14/2018 | 12/14/2018 | 12/14/2018 | A | DONE |
Mike Jordan
|
|
|
4.6ACH @50 pa.
|
BLD-Final | 12/13/2018 | 12/13/2018 | 12/13/2018 | P | PEND |
Mike Jordan
|
|
|
eric Phone #: ###-####. Everything ok. Needs blower door test.
|
BLD-Energy code compliance | 10/4/2018 | 10/5/2018 | 10/5/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Erik Wylie
|
BLD-Framing/Rough-in | 10/5/2018 | 10/5/2018 | 10/5/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Erik Wylie. All framing issues have bee resolved. Also reviewed Engineers letter regarding the portal frames, those issues hve been correctedas well. ok to cover.
|
BLD-Framing/Rough-in | 10/3/2018 | 10/3/2018 | 10/3/2018 | P | PART |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Erik Wylie C/N posted....Lateral truss bracing and strap.
|
BLD-Wall Bracing | 9/17/2018 | 9/18/2018 | 9/18/2018 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Erik Wylie. Provide the portal frames as shown on braced wall plans or provide engineering showing that the in place work is acceptable.
|
BLD-Framing/Rough-in | 9/4/2018 | 9/5/2018 | 9/5/2018 | A | PASS |
Mike Jordan
|
|
|
Eric Phone #: ###-####. Verified install and nailing of STHD14 hold downs prior to cover.
|
BLD-Foundation | 8/6/2018 | 8/7/2018 | 8/7/2018 | P | PART |
Mike Jordan
|
|
|
wall // Dane Phone #: ###-####
|
BLD-Footing | 8/3/2018 | 8/6/2018 | 8/6/2018 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|