BLD-Aging Inspection | 5/1/2020 | 5/1/2020 | 5/1/2020 | | DEFR |
Brandon Shaw
|
|
|
|
BLD-Aging Inspection | 4/30/2020 | 4/30/2020 | 4/30/2020 | | DEFR |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Foundation | 6/20/2019 | 6/21/2019 | 6/21/2019 | A | PASS |
Dave Hannah
|
|
|
late morning please- Willie Phone #: ###-####
|
BLD-Aging Inspection | 6/7/2019 | 6/7/2019 | 6/11/2019 | | PASS |
Tony Young
|
|
|
|
BLD-Footing | 6/10/2019 | 6/11/2019 | 6/11/2019 | A | PART |
Tony Young
|
|
|
Willie Phone #: ###-####,, west footings ok,, work in progress
|
BLD-Aging Inspection | 6/6/2019 | 6/6/2019 | 6/7/2019 | | PASS |
Tony Young
|
|
|
|
BLD-Wall Bracing | 1/22/2019 | 1/23/2019 | 1/23/2019 | A | CANC |
Mike Jordan
|
|
|
Kevin Phone #: ###-####
|
BLD-Foundation | 1/23/2019 | 1/23/2019 | 1/23/2019 | A | PASS |
Mike Jordan
|
|
|
Kevin Phone #: ###-####
|
BLD-Footing | 1/16/2019 | 1/17/2019 | 1/17/2019 | A | PASS |
Dave Hannah
|
|
|
1st thing in the AM if possible, kevin Phone #: ###-#### ftgs for house ok
|
BLD-Foundation | 11/16/2018 | 11/19/2018 | 11/19/2018 | A | PASS |
Tony Young
|
|
|
retaining wall - Kevin Phone #: ###-####,, 2nd lower wall ok
|
BLD-Foundation | 11/13/2018 | 11/13/2018 | 11/13/2018 | P | PART |
Tony Young
|
|
|
Cleeve-pour time 3:00 Phone #: ###-####,, work in progress on 2nd lower from the top on north,, ok
|
BLD-Foundation | 10/31/2018 | 11/1/2018 | 11/1/2018 | A | PART |
Brandon Shaw
|
|
|
Back retaining wall
|
BLD-Conference | 10/30/2018 | 10/30/2018 | 10/30/2018 | P | PART |
Tony Young
|
|
|
Cleve,, soils ok now upper retaining wall footings
|
BLD-Footing | 10/29/2018 | 10/30/2018 | 10/30/2018 | A | NR |
Mike Jordan
|
|
|
Cleve Phone #: ###-####, upper retaining wall. No soils report.
|
BLD-Footing | 10/29/2018 | 10/29/2018 | 10/29/2018 | P | NR |
Tony Young
|
|
|
Cleve Phone #: ###-####,, needs soils approval
|
BLD-Footing | 10/26/2018 | 10/29/2018 | 10/29/2018 | A | NR |
Tony Young
|
|
|
Cleve Phone #: ###-####,, needs soils approval
|