BLD-Final | 3/20/2019 | 3/20/2019 | 3/20/2019 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 3/20/2019 | 3/20/2019 | 3/20/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 3/18/2019 | 3/19/2019 | 3/19/2019 | P | PEND |
Mike Jordan
|
|
|
Ask for Stacie at the front desk. Plans are on the shelf by the new foundation Phone #: ###-#### Inspection requested via web by Clayn Sonderegger. Structural final ok. Will fianl when public works finals, mech and electrical finals.
|
FIRE-Final Inspection | 3/18/2019 | 3/18/2019 | 3/18/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 3/14/2019 | 3/15/2019 | 3/15/2019 | A | FAIL |
Jim Page
|
|
|
Waiting for verification of class 1 wiring and need suppression permit finaled.
Ask for Aaron or Mike at the front desk when you arrive. Phone #: ###-#### Inspection requested via web by Clayn Sonderegger
|
FIRE-Final Inspection | 3/13/2019 | 3/14/2019 | 3/14/2019 | P | FAIL |
Troy Cobbley
|
|
|
Waiting for verification of class 1 wiring and need suppression permit finaled.
|
FIRE-Final Inspection | 3/4/2019 | 3/5/2019 | 3/5/2019 | A | FAIL |
Troy Cobbley
|
|
|
See the city approved notes for items marked that need corrected. Items included exhaust clearance from hvac intake, 3' housekeeping clearance, signage, class 1 electrical and ventilation interlock.....ect.
Plans are on-site. Ask for Stacie at the front desk. Phone #: ###-#### Inspection requested via web by Clayn Sonderegger
|
BLD-Energy code compliance | 2/14/2019 | 2/15/2019 | 2/15/2019 | A | PASS |
Jim Sly
|
|
|
Plans are on rack by new foundation. Ask for Stacie at the front desk. We infilled the ceiling and exterior walls with insulation. Phone #: ###-#### Inspection requested via web by Clayn Sonderegger
|
BLD-Final | 2/14/2019 | 2/15/2019 | 2/15/2019 | A | NR |
Jim Sly
|
|
|
Plans are on rack by new foundation. Ask for Stacie at the front desk. We infilled the ceiling and exterior walls with insulation. Ready for final. Phone #: ###-#### Inspection requested via web by Clayn Sonderegger Talked to Clayn.........Gave him the list ......For finals to be completed, prior to calling for Structural final.
|
BLD-Foundation | 1/28/2019 | 1/29/2019 | 1/29/2019 | A | PASS |
Mike Jordan
|
|
|
We have concrete scheduled for 1:00pm. We should have the rebar in place by 10:00am. We do have MTI scheduled for rebar and cylinders, if required. This inspection is for one column footing. Phone #: ###-#### Inspection requested via web by Clayn Sonderegger
|