BLD-Final | 7/19/2019 | 7/22/2019 | 7/22/2019 | A | PASS |
Jim Storey
|
|
|
Mike Phone #: ###-####
|
FIRE-Final Inspection | 7/17/2019 | 7/19/2019 | 7/19/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, no fire alarm modifications, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete.
Michael Phone #: ###-####
|
FIRE-Conference | 7/2/2019 | 7/2/2019 | 7/2/2019 | A | DONE |
Jim Page
|
|
|
During my fire sprinkler inspection it was noticed that equipment was running, asked warehouse personnel if they were setting up equipment or if they were producing. I was informed that they were in fact producing. The fire sprinkler inspection has not been finaled for extra work, the electrical permit is in issued status as of this entry and no life fire safety inspection has been performed. I spoke with Gareth over the phone and informed him that production should not be happening until all inspections are complete and finaled for all permits associated with area of work.
|
FIRE-Conference | 5/16/2019 | 5/16/2019 | 5/16/2019 | P | DONE |
Jim Page
|
|
|
Fire conference complete, GC will need to contact a fire sprinkler contractor to fix blocked sprinkler head issues, elevated platforms and possible head addition under industrial containers.
Mike- please call Phone #: ###-####
|
FIRE-Final Inspection | 5/16/2019 | 5/16/2019 | 5/16/2019 | P | CANC |
Jim Page
|
|
|
Mike- please call Phone #: ###-####
|
BLD-Conference | 5/14/2019 | 5/14/2019 | 5/14/2019 | P | DONE |
Jim Storey
|
|
|
Michael Phone #: ###-####
|