BLD-Final | 3/27/2019 | 3/27/2019 | 3/27/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 3/27/2019 | 3/27/2019 | 3/27/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 3/27/2019 | 3/27/2019 | 3/27/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.87
|
BLD-Final | 3/21/2019 | 3/21/2019 | 3/21/2019 | P | NR |
Brandon Shaw
|
|
|
Need PLM and ELE finals...
|
BLD-Other | 1/24/2019 | 1/24/2019 | 1/24/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Energy code compliance | 1/24/2019 | 1/24/2019 | 1/24/2019 | P | PEND |
Brandon Shaw
|
|
|
Pending under floor and plumbing insulation...
|
BLD-Framing/Rough-in | 1/22/2019 | 1/23/2019 | 1/23/2019 | A | PEND |
Brandon Shaw
|
|
|
Remove dryer duct from garage seperation wall, as per discussion... OK to insulate...
|
BLD-Framing/Rough-in | 1/18/2019 | 1/22/2019 | 1/22/2019 | A | DEFR |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick// washer and dryer in the garage// membrane wall protection not clear as to how planreviewer meets code.
|
BLD-Wall Bracing | 12/20/2018 | 12/20/2018 | 12/20/2018 | A | PART |
Brandon Shaw
|
|
|
First floor only... Work in progress...
|
BLD-Footing | 11/27/2018 | 11/28/2018 | 11/28/2018 | A | CANC |
Brandon Shaw
|
|
|
Already poured
|
BLD-Foundation | 11/8/2018 | 11/8/2018 | 11/8/2018 | A | PASS |
Brandon Shaw
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 11/5/2018 | 11/6/2018 | 11/6/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 11/5/2018 | 11/6/2018 | 11/5/2018 | A | CANC |
Brandon Shaw
|
|
|
Inspection cancelled via mobile web on Monday, November 05, 2018.
|
BLD-Footing | 11/5/2018 | 11/5/2018 | 11/5/2018 | P | NR |
Dave Hannah
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell still working on spredding boards and no geo tect sign off
|