BLD-Final | 5/13/2019 | 5/13/2019 | 5/13/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
DOC - Permit Finaled | 5/13/2019 | 5/13/2019 | 5/13/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 5/13/2019 | 5/13/2019 | 5/13/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 4.5
|
BLD-Other | 5/13/2019 | 5/13/2019 | 5/13/2019 | P | CANC |
Brandon Shaw
|
|
|
Drainage test and landscaping final Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Other | 2/18/2019 | 2/19/2019 | 2/19/2019 | P | PASS |
Brandon Shaw
|
|
|
Soffit Please Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Energy code compliance | 2/13/2019 | 2/13/2019 | 2/13/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Energy code compliance | 2/11/2019 | 2/12/2019 | 2/12/2019 | P | NR |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 2/8/2019 | 2/8/2019 | 2/11/2019 | P | PART |
Brandon Shaw
|
|
|
Per plans- (3) 2x6 header needed at man door from garage... Anchor bolts to be no more than 12" from ends of sill plate... Positive connection required for 3 ply truss in garage, see orange paint...
|
BLD-Wall Bracing | 1/24/2019 | 1/24/2019 | 1/24/2019 | P | CANC |
Brandon Shaw
|
|
|
Work in progress... First floor only...
|
BLD-Foundation | 12/11/2018 | 12/11/2018 | 12/11/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress... Frost protection is required...
|
BLD-Footing | 12/10/2018 | 12/10/2018 | 12/10/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress... Frost protection required...
|
BLD-Footing | 12/6/2018 | 12/7/2018 | 12/7/2018 | A | NR |
Brandon Shaw
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 12/6/2018 | 12/6/2018 | 12/6/2018 | P | FAIL |
Brandon Shaw
|
|
|
As per ACI 318... forms, rebar, and soil sub-grade to be a minimum 35 F...
At itme of inspection, average sub-grade temp 11-32 F...
|