BLD-Final | 6/10/2019 | 6/11/2019 | 6/11/2019 | A | PASS |
Mike Jordan
|
|
|
Allen Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 6/6/2019 | 6/6/2019 | 6/6/2019 | P | CANC |
Troy Cobbley
|
|
|
Cody Phone #: ###-#### Inspection cancelled via mobile web on Thursday, June 06, 2019.
|
FIRE-Final Inspection | 6/6/2019 | 6/6/2019 | 6/6/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete.
|
BLD-Framing/Rough-in | 5/1/2019 | 5/1/2019 | 5/1/2019 | P | PASS |
Mike Jordan
|
|
|
Cody Phone #: ###-####. BAse layers for 3hr. fire barrier and partial 2nd. layer.
|
BLD-Conference | 4/24/2019 | 4/24/2019 | 4/24/2019 | P | DONE |
Mike Jordan
|
|
|
Todd Phone #: ###-####. Went over UL assembly for 3hr. fire barrier with contractor.
|
BLD-Framing/Rough-in | 4/23/2019 | 4/23/2019 | 4/23/2019 | P | PART |
Mike Jordan
|
|
|
Todd Phone #: ###-####. Interior steel stud framed walls, except for 3hr. hr fire barier ok for cover. Pending plumbing rough in inspection.
|
BLD-Conference | 4/16/2019 | 4/17/2019 | 4/17/2019 | A | DONE |
Mike Jordan
|
|
|
Call half hour before to meet // Allen Phone #: ###-####
|
BLD-Framing/Rough-in | 4/11/2019 | 4/12/2019 | 4/12/2019 | A | PART |
Mike Jordan
|
|
|
Jr. Phone #: ###-####. Interior steel atud framed walls for 3hr. fire barier.
|