BLD-Final | 9/9/2019 | 9/10/2019 | 9/10/2019 | A | PASS |
Mike Jordan
|
|
|
Brandon Phone #: ###-####
|
DOC - Permit Finaled | 9/10/2019 | 9/10/2019 | 9/10/2019 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 9/4/2019 | 9/4/2019 | 9/4/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Card signed. Brandon Phone #: ###-####
|
BLD-Framing/Rough-in | 8/29/2019 | 8/30/2019 | 8/30/2019 | A | PASS |
Mike Jordan
|
|
|
Brandon Phone #: ###-####. Beyween noon and two. All issues regarding through penetrations for new tub drains has been resolved.
|
BLD-Conference | 8/28/2019 | 8/29/2019 | 8/29/2019 | A | CANC |
Mike Jordan
|
|
|
Brandon Phone #: ###-####. Moved to friday 8-30.
|
BLD-Final | 7/25/2019 | 7/26/2019 | 7/26/2019 | A | PART |
Tell Riley
|
|
|
Brandon Phone #: ###-####//temp occupancy for offices behind lobby area//
|
FIRE-Final Inspection | 7/24/2019 | 7/25/2019 | 7/25/2019 | P | PART |
Troy Cobbley
|
|
|
Life safety is being given a partial for the remodeled office area behind the new check-in counter. Brandon Phone #: ###-####
|
BLD-Final | 7/24/2019 | 7/25/2019 | 7/25/2019 | A | PART |
Tell Riley
|
|
|
Brandon ###-####//need to verify with Troy for temp occupancy for lobby area only//ok for temp occupancy for reception area//do not occupy office areas and back room until all inspections complete//
|
BLD-Final | 7/23/2019 | 7/24/2019 | 7/24/2019 | P | CANC |
Tell Riley
|
|
|
Brandon Phone #: ###-####
|
FIRE-Final Inspection | 7/24/2019 | 7/25/2019 | 7/24/2019 | A | PART |
Troy Cobbley
|
|
|
Life safety is passed for the Lobby area but not the back office area. Per discussion emergency lighting will be required for the existing lobby prior to a final sign off just as it is being required at the bottom of both stairwells.
Brandon Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/1/2019 | 7/2/2019 | 7/2/2019 | A | PASS |
Mike Jordan
|
|
|
Uri Phone #: ###-####
|
BLD-Final | 7/2/2019 | 7/3/2019 | 7/2/2019 | P | CANC |
Mike Jordan
|
|
|
cancel per Yuiry Yuriy Phone #: ###-####
|
FIRE-Final Inspection | 7/2/2019 | 7/3/2019 | 7/2/2019 | A | CANC |
Troy Cobbley
|
|
|
cancel per Yuiry Yuriy Phone #: ###-####
|
BLD-Framing/Rough-in | 6/26/2019 | 6/26/2019 | 6/26/2019 | P | PASS |
Mike Jordan
|
|
|
2 layers of 5/8 type X rock for previously unprotected beam ok for cover.
|
BLD-Framing/Rough-in | 6/25/2019 | 6/26/2019 | 6/26/2019 | P | CANC |
Mike Jordan
|
|
|
yurry Phone #: ###-####.
|
BLD-Final | 6/19/2019 | 6/20/2019 | 6/20/2019 | P | PART |
Mike Jordan
|
|
|
Yury-1st floor minus the front desk and back office Phone #: ###-####. Ok to occupy 1st. floor except for main lobby area.
|
FIRE-Final Inspection | 6/19/2019 | 6/20/2019 | 6/20/2019 | A | PART |
Troy Cobbley
|
|
|
Life safety for the first floor, except for the Main Lobby and associated back office passed.
Yury-1st floor minus the front desk and back office Phone #: ###-####
|
BLD-Conference | 6/12/2019 | 6/13/2019 | 6/13/2019 | A | DONE |
Mike Jordan
|
|
|
Eri Phone #: ###-####
|
BLD-Framing/Rough-in | 5/30/2019 | 5/31/2019 | 5/31/2019 | A | FAIL |
Jim Storey
|
|
|
Yurri Phone #: ###-#### II a const. beam in lobby unprotected. sub mit to planreview as to how to address.
|
BLD-Framing/Rough-in | 5/29/2019 | 5/30/2019 | 5/30/2019 | A | PART |
Mike Jordan
|
|
|
Jery Phone #: ###-####. Interior steel stud framed walls in lobby area only ok. Needs t patch sheetrock at floor ceiling assemblies and fircaulk all penetrations. A mech permit is also required for the new duct work that was added in drop down ceiling area. A plan mod or a seperate building permit is also required for the repair of the porte cochere. A correction notice was issued.
|
BLD-Framing/Rough-in | 5/23/2019 | 5/23/2019 | 5/24/2019 | P | NR |
Dave Hannah
|
|
|
reception area // Yuri Phone #: ###-####
|
BLD-Conference | 4/29/2019 | 4/29/2019 | 4/29/2019 | P | DONE |
Mike Jordan
|
|
|
The correct fire caulking on 1st. floor has now been used.
|
BLD-Conference | 4/29/2019 | 4/29/2019 | 4/29/2019 | A | FAIL |
Mike Jordan
|
|
|
Noted that caulking used is a fire block and not a UL listed fire stop. Contractor to insatll correct materials and will reinspect this afternoon. A correction notice was also issued to fire stop all tub drains and plumbing penetrations for new lavs on the 3rd and 4th floors, to maintain the exisiting fire protection.
|
BLD-Conference | 4/25/2019 | 4/26/2019 | 4/26/2019 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Conference | 4/25/2019 | 4/25/2019 | 4/25/2019 | P | DONE |
Mike Jordan
|
|
|
|
BLD-Final | 4/19/2019 | 4/24/2019 | 4/24/2019 | A | CANC |
Mike Jordan
|
|
|
1st, 2nd and 3rd // Yuriy Phone #: ###-####
|
BLD-Conference | 4/24/2019 | 4/24/2019 | 4/24/2019 | A | DONE |
Mike Jordan
|
|
|
1st, 2nd and 3rd // Yuriy Phone #: ###-####
|
BLD-Final | 4/17/2019 | 4/18/2019 | 4/18/2019 | P | PART |
Mike Jordan
|
|
|
Steve Phone #: ###-####. OPK to occupy 2nf. floor.
|
BLD-Final | 4/16/2019 | 4/17/2019 | 4/17/2019 | P | NR |
Mike Jordan
|
|
|
2nd floor // Steve Phone #: ###-####. Needs electrical final.
|
FIRE-Final Inspection | 4/16/2019 | 4/17/2019 | 4/17/2019 | A | PART |
Troy Cobbley
|
|
|
Life safety for the 2nd floor passed.// Steve Phone #: ###-####
|
BLD-Final | 2/21/2019 | 2/22/2019 | 2/22/2019 | P | PART |
Mike Jordan
|
|
|
3rd floor // Steve Phone #: ###-####. Ok to occupy 3rd floor.
|
FIRE-Final Inspection | 2/21/2019 | 2/22/2019 | 2/22/2019 | A | PART |
Troy Cobbley
|
|
|
Temp for life safety on 3rd floor. Contractor had to remove the new LED bulbs from the emergency lights and re-install the old bulbs for them to work on battery back up. // Steve Phone #: ###-####
|
BLD-Final | 2/14/2019 | 2/15/2019 | 2/15/2019 | P | PART |
Jim Sly
|
|
|
Steve- wants partial on the 4th floor for a temp c of o Phone #: ###-#### Temp OK for 4th floor ........Only.
|
FIRE-Final Inspection | 2/15/2019 | 2/15/2019 | 2/15/2019 | P | PART |
Jim Page
|
|
|
Life fire safety inspection for level 4 complete. Stairwells to remain clear with no storage once TCO is authorized.
|
FIRE-Final Inspection | 2/14/2019 | 2/15/2019 | 2/15/2019 | A | FAIL |
Jim Page
|
|
|
Left a voicemail with point of contact provided, waited for 30 minutes to recieve a return call, no return call was made, proceeded to next inspection, this request will need to be rescheduled.
Steve- wants partial on the 4th floor for a temp c of o Phone #: ###-####
|
BLD-Conference | 8/15/2019 | 8/16/2019 | | A | |
Mike Jordan
|
|
|
Brandon Hout Phone #: ###-####
|
BLD-Conference | 4/26/2019 | 4/26/2019 | | P | |
Mike Jordan
|
|
|
|