BLD-Final | 5/2/2019 | 5/2/2019 | 5/2/2019 | P | PASS |
Dave Hannah
|
|
|
Nicol Phone #: ###-#### ok for perm occ once MEC passes- per David H (MEC Final Complete 5/29/19 TCH)
|
FIRE-Final Inspection | 5/1/2019 | 5/2/2019 | 5/2/2019 | A | PASS |
Mark Scharfen
|
|
|
Verified extinguisher in place. Had verified Exit lights on 4/30. PASSED.
Nicol Phone #: ###-####
|
FIRE-Conference | 5/1/2019 | 5/1/2019 | 5/1/2019 | P | DONE |
Troy Cobbley
|
|
|
Per the general contractor a barrier is going to be installed above the cooler to provide separation.
|
BLD-Final | 5/1/2019 | 5/1/2019 | 5/1/2019 | P | CANC |
Dave Hannah
|
|
|
Nicol Phone #: ###-####
Nico canceled
|
FIRE-Final Inspection | 5/1/2019 | 5/1/2019 | 5/1/2019 | P | CANC |
Jim Page
|
|
|
Nicol Phone #: ###-####
Nico canceled
|
FIRE-Final Inspection | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | FAIL |
Mark Scharfen
|
|
|
Fire extinguishers are not installed will need to be on reinspection. Pocket door was noted and will be reviewed by building inspector.
Nicol Phone #: ###-####
|
BLD-Wall cover | 2/21/2019 | 2/22/2019 | 2/22/2019 | P | PASS |
Dave Hannah
|
|
|
Nicol Phone #: ###-####
|
BLD-Conference | 2/5/2019 | 2/6/2019 | 2/6/2019 | A | PART |
Dave Hannah
|
|
|
Nicol Phone #: ###-#### to to rock top of walls
|