BLD-Final | 3/18/2020 | 3/18/2020 | 3/18/2020 | P | PASS |
Mike Jordan
|
|
|
Ian Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 3/16/2020 | 3/17/2020 | 3/17/2020 | A | FAIL |
Mike Jordan
|
|
|
Ian Phone #: ###-####. Complete fire caulking in stair towers.
|
BLD-Final | 3/13/2020 | 3/16/2020 | 3/16/2020 | A | NR |
Jim Storey
|
|
|
Pierre Phone #: ###-#### need card signed pw and p$z
|
FIRE-Final Inspection | 3/13/2020 | 3/13/2020 | 3/13/2020 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Ian Phone #: ###-####
|
BLD-Final | 1/31/2020 | 2/3/2020 | 2/3/2020 | P | NR |
Mike Jordan
|
|
|
Glen Phone #: ###-####
|
FIRE-Final Inspection | 1/31/2020 | 2/3/2020 | 2/3/2020 | A | FAIL |
Troy Cobbley
|
|
|
Failed based on noted deficiencies: secondary gate needed opticon installed., tested and pavement, primary gate needed opticon tested and pavement installed, clearanced between AC unit ballard and fence was less than 20 foot required clearance north end of blding 2, site and blding addrss numbers/letters need to be provided as per discussion, provide most up to date review comments.
Glen Phone #: ###-####
|
BLD-Footing | 8/21/2019 | 8/22/2019 | 8/22/2019 | A | PASS |
Mike Jordan
|
|
|
footing and rebar Phone #: ###-#### Inspection requested via web by Glen Farrell
|
BLD-Footing | 7/18/2019 | 7/19/2019 | 7/19/2019 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Glen Farrell
|